Two years after large sinkholes opened above the construction of a $3.1bn Sydney motorway tunnel, the consortium charged with the project’s completion has been issued a notice forcing it to continue the job or face possible legal consequences.
The New South Wales roads minister, Jenny Aitchison, said contractor CGU had on Monday been issued a “notice of default”, forcing it to recommence work on the 90% complete M6 tunnel by 1 May.
Excavation on the tunnel in Kogarah had been on hold since the sinkholes formed in March 2024 and a “challenging” geological feature was discovered close by, with works eventually grinding to a halt last June after the contractor claimed a design solution could not be achieved.
Drone vision shows sinkhole beneath Sydney building – video
At the time, the NSW premier, Chris Minns, criticised the unilateral move to down tools, claiming the contractor remained responsible for designing and building the tunnels.
Aitchison said the government had taken “decisive action” after attempting to remedy the impasse, including by presenting an engineering solution to CGU, a joint venture of CPB, Ghella and UGL.
Sign up: AU Breaking News email
“Transport for NSW has issued a notice of default to CGU after more than two years of work to try to resolve the issues affecting this project,” she said in a statement on Monday.
“The department has made clear there is a technical solution available within the current contract – and it is a reasonable community expectation that it is delivered.”
The new twin 4km tunnels, connecting Sydney’s south to the wider motorway network, were approved in 2019 and scheduled to open in 2025. That date was pushed back to 2028 after the sinkholes opened, then workers discovered a “high-angle reverse fault” in the bedrock in the same 245-metre section of the project.
In NSW transport estimates on Tuesday, Aitchison said CGU had concerns it could not deliver the project safely and viably, but she expected the company to meet its obligations.
“We are holding the contractor to account to their commitments that they made when they signed the contract,” she told the committee. “I’m hopeful that we can come to a resolution.”
She said she could not provide information about additional costs or a possible finishing date because of ongoing legal negotiations, but the premier had previously ruled out spending any additional money on the project.
Nor had the contractor approached her office to make a formal request for more funding for the project, Aitchison said.
Minns ruled out any further funding on Tuesday when asked whether the government may need to compromise if CGU was unable to cover the “additional $1.5bn required to fix the tunnels”.
“No. This contractor … took the risk on design and they took the risk on construction,” he told reporters.
“I’m sorry it hasn’t worked out, but at the end of the day, they have to make good on it – they’re a big international infrastructure company, they signed a deal with the NSW government. I promise you, if they came in under budget, they wouldn’t be sending us a cheque back, so they’re going to have to step up.”
When asked by the Nationals MLC Nichole Overall whether the government was “prepared to let the project collapse, effectively letting a $3.1bn project turn into a white elephant”, the minister said she would not prejudice legal discussions “with comments made here to satisfy your scaremongering”.
The NSW government has so far spent $5m on legal fees in the dispute, the committee heard.
CPB, as the lead contractor for CGU, was approached for comment.
Get in touch
Contact Guardian Australia
If you have something to share about this story, you can contact Guardian Australia’s news teams using one of the following methods:
Secure Messaging in the Guardian app
The Guardian app has a tool to send tips about stories. Messages are end to end encrypted and concealed within the routine activity that every Guardian mobile app performs. This prevents an observer from knowing that you are communicating with us at all, let alone what is being said.
If you don’t already have the Guardian app, download it (iOS/Android) and go to the menu. Select ‘Secure Messaging’.
If you don’t need strong security you can write to a Guardian Australia journalist using the details here. Click on a person to see their details.
For end to end encrypted email you can create a free Proton Mail account and email gaus.contact@protonmail.com.
Messaging apps
You can use the encrypted messaging apps Signal or WhatsApp to message us at +61 490 758 250.
SecureDropIf you can safely use the tor network without being observed or monitored you can send messages and documents to the Guardian via our SecureDrop platform.
Finally, our guide at theguardian.com/tips lists several ways to contact us securely, and discusses the pros and cons of each.
Show more