{"id":746995,"date":"2026-06-19T16:07:13","date_gmt":"2026-06-19T16:07:13","guid":{"rendered":"https:\/\/www.newsbeep.com\/au\/746995\/"},"modified":"2026-06-19T16:07:13","modified_gmt":"2026-06-19T16:07:13","slug":"sydneys-unbuildable-motorway-to-be-completed-after-two-year-delay-caused-by-sinkholes-new-south-wales","status":"publish","type":"post","link":"https:\/\/www.newsbeep.com\/au\/746995\/","title":{"rendered":"Sydney\u2019s \u2018unbuildable motorway\u2019 to be completed after two-year delay caused by sinkholes | New South Wales"},"content":{"rendered":"<p class=\"dcr-130mj7b\">Tunnelling on Sydney\u2019s $3.1bn M6 project, dubbed the potentially \u201c<a href=\"https:\/\/www.theguardian.com\/australia-news\/2025\/jun\/29\/could-the-m6-be-sydneys-unbuildable-motorway-due-to-sinkholes-and-a-reverse-fault\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">unbuildable motorway<\/a>\u201d, will resume after the state government struck a deal with contractors, ending a two-year stalemate during which works were halted.<\/p>\n<p class=\"dcr-130mj7b\">Under the terms of the new agreement, the private consortium will absorb the costs of finishing the tunnels, limiting the financial hit to taxpayers.<\/p>\n<p class=\"dcr-130mj7b\">Motorists will still need to wait, however, with the M6 now scheduled to open in 2028 at the earliest.<\/p>\n<p class=\"dcr-130mj7b\">The project, which consists of twin 4km tunnels connecting Sydney\u2019s south to the wider road network, was initially approved in 2019 under the former Coalition government with an original completion date of 2024. That was later pushed back to 2025.<\/p>\n<p>Sinkholes and a reverse fault<\/p>\n<p class=\"dcr-130mj7b\">Tunnelling was 90% complete when <a href=\"https:\/\/www.theguardian.com\/australia-news\/2024\/mar\/01\/sydney-sinkhole-rockdale-workers-evacuated\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">two large sinkholes opened<\/a> in March 2024 above the tunnel and below an industrial estate in Rockdale, throwing the project into disarray.<\/p>\n<p class=\"dcr-130mj7b\">Underground works on the tunnels linking Kogarah and Arncliffe ceased altogether in June 2025. The consortium charged with completing the M6 said it would <a href=\"https:\/\/www.theguardian.com\/australia-news\/2025\/jun\/29\/could-the-m6-be-sydneys-unbuildable-motorway-due-to-sinkholes-and-a-reverse-fault\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">down tools after the discovery of a \u201chigh-angle reverse fault\u201d<\/a> \u2013 where a layer of rock is forced upwards and over another layer \u2013 in the bedrock close to the sinkholes.<\/p>\n<p><a data-name=\"placeholder\" href=\"https:\/\/interactive.guim.co.uk\/uploader\/embed\/2025\/06\/archive-zip\/giv-32554gYxLrcoY8Fxe\/\" class=\"dcr-1eupayo\" rel=\"nofollow noopener\" target=\"_blank\">M6 map<\/a><\/p>\n<p class=\"dcr-130mj7b\">The crisis was ventilated in May 2025, when the <a href=\"https:\/\/www.smh.com.au\/politics\/nsw\/contractor-walks-away-from-m6-after-sinkholes-derail-project-20250502-p5lvyw.html\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">Sydney Morning Herald<\/a> published a leaked email to staff from David Jackson, the director of the project\u2019s first stage, stating that the joint venture was pulling out.<\/p>\n<p class=\"dcr-130mj7b\">Friday\u2019s agreement looks to settle the two-year dispute between the <a href=\"https:\/\/www.theguardian.com\/australia-news\/new-south-wales\" data-link-name=\"in body link\" data-component=\"auto-linked-tag\" rel=\"nofollow noopener\" target=\"_blank\">New South Wales<\/a> government and the CPB Contractors-led consortium over who should pay to complete the compromised tunnels.<\/p>\n<p class=\"dcr-130mj7b\">The government said the consortium \u2013 a joint venture of CPB, Ghella and UGL, known collectively as CGU \u2013 had agreed not to pursue contractual claims against the state for costs related to the 2024 sinkholes.<\/p>\n<p class=\"dcr-130mj7b\">With 250 metres of excavation remaining on the main tunnel, the NSW Motorways chief executive, Camilla Drover, said CGU would complete the project as per the terms of the contract.<\/p>\n<p class=\"dcr-130mj7b\">\u201cCGU will resume work on the project immediately, and we will provide an updated timeline for expected completion once we have it,\u201d she said.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" alt=\"Drone vision shows sinkhole beneath Sydney building \u2013 video\" src=\"https:\/\/www.newsbeep.com\/au\/wp-content\/uploads\/2026\/06\/1310.jpg\" height=\"259\" width=\"460\" class=\"dcr-1qi2at0\"\/>Drone vision shows sinkhole beneath Sydney building \u2013 video<\/p>\n<p class=\"dcr-130mj7b\">The NSW roads minister, Jenny Aitchison, said work would resume immediately and at no additional cost to the public.<\/p>\n<p class=\"dcr-130mj7b\">\u201cOur priority has always been to complete this project under the existing contract,\u201d she said on Friday. \u201cUnlike the Liberals, we will not hand out blank cheques when contractors try to take NSW taxpayers for a ride.\u201d<\/p>\n<p class=\"dcr-130mj7b\">The breakthrough follows a revelation that the government <a href=\"https:\/\/www.smh.com.au\/national\/nsw\/abandoning-nearly-built-motorway-in-sydney-s-south-secretly-explored-20260604-p603z0.html\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">reportedly explored abandoning the project<\/a> during the standoff.<\/p>\n<p class=\"dcr-130mj7b\">Josh Murray, the Transport for NSW secretary, said CGU would be responsible for rectifying the \u201csubsidence issue that originally paused the contract\u201d.<\/p>\n<p class=\"dcr-130mj7b\">\u201cWhile there has been a regrettable delay, the contract for the M6 Stage 1 has clear dispute resolution processes and these will be used,\u201d he said in a statement.<\/p>\n<p class=\"dcr-130mj7b\">CPB was contacted for comment. CPB\u2019s executive project director, <a href=\"https:\/\/www.smh.com.au\/national\/nsw\/tunnelling-to-restart-on-sydney-motorway-two-years-after-sinkholes-halt-work-20260617-p607ki.html#:~:text=CPB%20executive%20project%20director%20Terry%20Sleiman%20confirmed%20an%20agreement%20had%20been%20reached%20with%20Transport%20for%20NSW%2C%20welcoming%20the%20%E2%80%9Copportunity%20to%20continue%20tunnelling%20works%E2%80%9D%20on%20the%20project.\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">Terry Sleiman, told the SMH<\/a> the agreement provided the \u201copportunity to continue tunnelling works\u201d.<\/p>\n<p>Jet grouting<\/p>\n<p class=\"dcr-130mj7b\">To complete the remaining 250 metres, contractors could use an engineering method known as \u201c<a href=\"https:\/\/sear.unisq.edu.au\/2236\/1\/CHOI_RichardFunYiu-2005.pdf\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">jet grouting<\/a>\u201d, which employs high-speed fluid to erode soil, with the resulting cavity filled with grout to form a composite material.<\/p>\n<p class=\"dcr-130mj7b\">Grahame Campbell, an engineer who project-managed the M4, delivering it in half the forecast time and budget, welcomed Friday\u2019s resolution but said the situation was avoidable.<\/p>\n<p>An artist\u2019s rendering of how the completed M6 entrance could look. Illustration: Transport for NSW<\/p>\n<p class=\"dcr-130mj7b\">Campbell, who authored <a href=\"https:\/\/www.cis.org.au\/publication\/bungles-blowouts-and-boondoggles-why-australias-infrastructure-projects-cost-more-than-they-should\/\" data-link-name=\"in body link\" rel=\"nofollow noopener\" target=\"_blank\">a research paper<\/a> for the Centre for Independent Studies about \u201cbungles\u201d that drive up project timelines and costs across Australia, said jet grouting was the only viable option.<\/p>\n<p class=\"dcr-130mj7b\">\u201cIt\u2019s good to read that they have finally decided to sort out the contract after this protracted delay,\u201d he said. \u201c[Jet grouting] is used to solidify the rock so it can be drilled and tunnelled.\u201d<\/p>\n<p class=\"dcr-130mj7b\">Campbell said the two-year pause highlighted a systemic failure by governments to conduct necessary preliminary geological work before signing major infrastructure contracts.<\/p>\n<p class=\"dcr-130mj7b\">\u201cThey should have done more investigation into the geology under the road system,\u201d he said on Friday.<\/p>\n<p class=\"dcr-130mj7b\">\u201cThat\u2019s the main reason it went over budget. Disputes are common because the government doesn\u2019t do the preliminary work necessary to fully define the terms of the contracts.\u201d<\/p>\n","protected":false},"excerpt":{"rendered":"Tunnelling on Sydney\u2019s $3.1bn M6 project, dubbed the potentially \u201cunbuildable motorway\u201d, will resume after the state government struck&hellip;\n","protected":false},"author":2,"featured_media":746996,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[2],"tags":[43,44,41,39,42,40],"class_list":["post-746995","post","type-post","status-publish","format-standard","has-post-thumbnail","category-headlines","tag-headlines","tag-news","tag-top-news","tag-top-stories","tag-topnews","tag-topstories"],"_links":{"self":[{"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/posts\/746995","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/comments?post=746995"}],"version-history":[{"count":0,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/posts\/746995\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/media\/746996"}],"wp:attachment":[{"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/media?parent=746995"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/categories?post=746995"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.newsbeep.com\/au\/wp-json\/wp\/v2\/tags?post=746995"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}