On March 13, 2026, crews began installing rebar around the exposed Bearspaw South Feeder Main.
On March 13, 2026, crews began installing rebar around the exposed Bearspaw South Feeder Main.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/excavate-two-segments-march-13-0014.JPG
On March 12, 2026 crews excavate two segments of the Bearspaw South Feeder Main for reinforcement work, on 16 Avenue N.W. near the Sarcee Trail N.W. interchange.
On March 12, 2026 crews excavate two segments of the Bearspaw South Feeder Main for reinforcement work, on 16 Avenue N.W. near the Sarcee Trail N.W. interchange.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/bearspaw-south-trench-boxes-022.JPG
Nine segments of the Bearspaw South Feeder Main are being reinforced to support the pipes stability. On March 13, 2026, crews continued to construct trench boxes and began installing rebar around the exposed pipe.
Nine segments of the Bearspaw South Feeder Main are being reinforced to support the pipes stability. On March 13, 2026, crews continued to construct trench boxes and began installing rebar around the exposed pipe.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/nine-segments-reinforced-excavate-004.JPG
On March 12, 2026, the nine segments of the Bearspaw South Feeder Main that are being reinforced have been excavated and trench boxes are being built around the pipe.
On March 12, 2026, the nine segments of the Bearspaw South Feeder Main that are being reinforced have been excavated and trench boxes are being built around the pipe.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/excavation-segments-008.JPG
Two segments of the Bearspaw South Feeder Main have been excavated on 16 Avenue N.W. near the Sarcee Trail N.W. interchange on March 12, 2026.
Two segments of the Bearspaw South Feeder Main have been excavated on 16 Avenue N.W. near the Sarcee Trail N.W. interchange on March 12, 2026.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/bearspaw-concrete-pour-march-16-2.JPG
March 16, 2026, Image shows the first concrete encasement pour to begin on the Bearspaw South Feeder Main.Â
March 16, 2026, Image shows the first concrete encasement pour to begin on the Bearspaw South Feeder Main.Â
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/bearspaw-concrete-pour-March-16-1.JPG
The first concrete pour on the Bearspaw South Feeder Main began on March 16, 2026.
The first concrete pour on the Bearspaw South Feeder Main began on March 16, 2026.
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/concrete-pour-16-ave-sarcee-002.JPG
On March 19, crews are monitoring the site where concrete has been poured and is now curing at 16 Ave N.W. at the Sarcee interchange.Â
On March 19, crews are monitoring the site where concrete has been poured and is now curing at 16 Ave N.W. at the Sarcee interchange.Â
/content/dam/www/is/utilities-delivery/bearspaw-feeder-main/reinforcement-gallery/point-mckay-microtunnel-shaft-011.JPG
On March 19, crews work near Point McKay Park where a microtunnelling shaft can be seen for the Bearspaw South Replacement Project and concrete curing for the reinforcement work on the Bearspaw South Feeder Main.
On March 19, crews work near Point McKay Park where a microtunnelling shaft can be seen for the Bearspaw South Replacement Project and concrete curing for the reinforcement work on the Bearspaw South Feeder Main.