A portion of the abandoned Amazon data centre site in northwest Auckland. Photo / Chris Keall
ADS 2025 headline numbers
Net service sales: $124.0m (2024: $68.9m)Profit: -$37.5m ($4.7m)Income tax: Provision $735,000 ($1.5m)
AWS 2025 headline numbers
Net service sales: $479.5m (2024: $425.7m)Profit: $14.3m ($26.3m)Income tax: -$4.89m (-$4.87m)
Microsoft – which also gained Overseas Investment Office permission to buy land at Westgate, did go ahead with its $1 billion build. Brookfield-owned DCI built a data centre, immediately to the rear. Amazon’s data centre would have been to the right. Microsoft gained OIO approval to buy two sites (the other is near the air base at Whenuapai) but has so far only built on one. Photo / Chris
Tax advocate questions service fee
A marketing map produced by NZRPG showing the (ultimately abandoned) site of the Amazon build. Map / NZ Retail Property Group