Wellington City councillors have voted not to continue with the controversial $139 million Golden Mile project.

The upgrade of the Golden Mile, which stretches from the Lambton Quay to Courtenay Place, sought to remove cars from the latter during the day, widen foot paths, create a cycle lane, and improve lighting.

It would also line the street with anti-slip pavement and new greenery, and replace old water pipes that are sitting under the thoroughfare.

The project was scoped in 2021, with the $139m price tag being funded 49 percent by council and 51 percent by the Transport Agency.

The council voted in November to pause and review the project after cost estimates grew from $139m to $220 million.

Today’s vote passed 14 to 3, with Laurie Foon, Geordie Rogers and Rebecca Matthews those opposed.

Karl Tiefenbacher, who owns Kaffee Eis which has a store on Courtenay Place, was excluded from the vote due to a conflict of interest.

Work had already begun at the intersection of Cambridge and Kent Terraces last year and council officers were recommending $1.5m of council funding be retained for make-safe works.

Council officers were directed to report back on on cheaper targeted Golden Mile transport corridor improvements and Courtenay Place urban regeneration. They would be capped at $20-$40m council investment and seek to optimise NZTA co-funding.

A total of $150,000 from the City Growth Fund was also approved to support the Te Aro Hā business partnership – a group of local businesses and property owners – to make visible improvements in Courtenay Place over the next 12 months such as façade upgrades, painting, lighting, signage and other low-cost works that improve attractiveness and perceptions of the area.

Officers were also to report back with options for establishing a Precinct Accelerator Fund, to further support co-investment initiatives to improve the public realm in the medium term.

The council also voted deep cleaning of Courtenay Place would also increase from monthly to weekly, an additional $91,000 per year.

Community needs certainty, Mayor says

Mayor Andrew Little said businesses up and down the Golden Mile had been waiting a long time to see what would happen, and the community needed certainty.

He said they were in a climate where several projects including the Town Hall and the Sludge Minimisation Facility had gone considerably over budget.

“The price of those projects going considerably over budget in some circumstances is that it constrains our future options and this is what’s being constrained.”

Wellington Mayor Andrew Little speaks to media after the government announced further cuts to public service jobs on 19 May, 2026.

Wellington Mayor Andrew Little.

RNZ / Samuel Rillstone

Nicola Young said she had “endured” the Golden Mile project from the start and was “delighted” to finally see a sensible proposal.

Afnan Al-Rubayee said she believed in the aspirations of the Golden Mile, but the council also had to be practical.

“We need to finally deliver something. Wellingtonians can’t afford to keep waiting and they don’t want to,” she said.

“As elected members, I believe that our role is not to only dream for Wellington, but to be good stewards of public resources and responsibly.”

Geordie Rogers said he hoped to see the council invest in Courtenay Place “and we don’t just start another 10-year cycle failing to deliver a tin mile when we could have had a golden one”.

Rebecca Mathews expressed concerns of kissing goodbye nearly $70 million of government funding.

“Wellington has been let down by some of its elected members and by this organisation, in my opinion.”

Laurie Foon said $12m had already been spent on the Golden Mile and she believed the current council lacked vision and direction.