{"id":343702,"date":"2026-03-23T13:01:58","date_gmt":"2026-03-23T13:01:58","guid":{"rendered":"https:\/\/www.newsbeep.com\/nz\/343702\/"},"modified":"2026-03-23T13:01:58","modified_gmt":"2026-03-23T13:01:58","slug":"moa-point-report-reveals-air-bubble-may-have-caused-massive-failure","status":"publish","type":"post","link":"https:\/\/www.newsbeep.com\/nz\/343702\/","title":{"rendered":"Moa Point report reveals air bubble may have caused massive failure"},"content":{"rendered":"<p>The catastrophic failure of the Moa Point wastewater treatment plant may have been caused by air trapped in the pipes, a <a href=\"https:\/\/www.rnz.co.nz\/news\/national\/589949\/moa-point-failure-report-to-be-released-on-friday\" rel=\"nofollow noopener\" target=\"_blank\">report<\/a> has revealed.<\/p>\n<p>The Wellington plant failed last month, flooding the facility and sending millions of litres of raw sewage into the sea each day.<\/p>\n<p>Wellington City Council on Friday released the first report into the ongoing saga.<\/p>\n<p>Wellington Water commissioned the engineering report on 5 February &#8211; the day after the failure &#8211; to understand how the plant could be operated during the recovery.<\/p>\n<p>Experts from Stantec used software to develop a hydraulic model of the plant, and replicated the likely flow of water running through the plant when it failed.<\/p>\n<p>While the report was not commissioned to identify the cause, it had revealed valuable information, Wellington Mayor Andrew Little&#8217;s office said.<\/p>\n<p><img decoding=\"async\" loading=\"lazy\" src=\"https:\/\/www.newsbeep.com\/nz\/wp-content\/uploads\/2026\/03\/4JRGY0V_Image_2_jfif.jpeg\" width=\"1050\" height=\"700\" alt=\"Wellington City Council on Friday released the first report into the ongoing saga.\"\/><\/p>\n<p class=\"photo-captioned__information\">\nWellington Mayor Andrew Little said the report was just one piece of the puzzle.<br \/>\nPhoto: RNZ \/ Samuel Rillstone\n<\/p>\n<p>&#8220;The report found that air can become trapped in the wastewater bypass pipeline, particularly when there is a high flow of wastewater passing through the plant.<\/p>\n<p>&#8220;It is possible that trapped air could disrupt the flow of wastewater, pushing it backwards and flooding the plant.&#8221;<\/p>\n<p>There was a &#8220;significant risk&#8221; of the air being trapped in the system, causing a &#8220;choke point&#8221; the report said.<\/p>\n<p>And if it did happen, it would be &#8220;a likely cause of the flooding&#8221;.<\/p>\n<p>The bypass system allows screened wastewater to bypass further treatment &#8211; like disinfection &#8211; and be discharged out to sea when the plant is at maximum capacity.<\/p>\n<p>At a media conference on Friday afternoon, Wellington Water&#8217;s Chief Operating Officer Charles Barker said it was &#8220;clearly evident&#8221; that the air pocket problem was a factor in the plant&#8217;s failure.<\/p>\n<p>He described what could have happened: &#8220;Sometimes you pull the plug out of your sink, and it doesn&#8217;t go down as fast as you think, because it starts going glug, glug, glug, glug, glug&#8230; it&#8217;s that type of effect.<\/p>\n<p>&#8220;A certain amount of air is good in a steady state, when it gets all mixed up together, the water &#8230; starts behaving differently.<\/p>\n<p>&#8220;It&#8217;s important to remember this is just not water trickling from a hose, this is thousands of litres per second under huge kind of speed.&#8221;<\/p>\n<p>Engineers suspected that potential cause almost immediately after it happened, he said.<\/p>\n<p><img decoding=\"async\" loading=\"lazy\" src=\"https:\/\/www.newsbeep.com\/nz\/wp-content\/uploads\/2026\/03\/4JRGY0V_Image_jfif.jpeg\" width=\"1050\" height=\"700\" alt=\"Wellington City Council on Friday released the first report into the ongoing saga.\"\/><\/p>\n<p class=\"photo-captioned__information\">\nWellington Water chief operating officer Charles Baker speaking to media following the release of the report.<br \/>\nPhoto: RNZ \/ Samuel Rillstone\n<\/p>\n<p>There were no staff on site at the time, but it was standard that it was not staffed overnight &#8211; not just at Moa Point but at plants around the world, Barker said.<\/p>\n<p>He confirmed the air block was not permanent, because the air &#8220;exists in a moment&#8221; and as the water flow drops away, &#8220;pipes can breathe again&#8221;.<\/p>\n<p>At the time, the plant&#8217;s UV system was being upgraded, so screened wastewater was diverted to the bypass pipe.<\/p>\n<p>Water entering that pipe could have become &#8220;turbulent&#8221;, dragging in air, becoming trapped and backing up the pipe.<\/p>\n<p>The report delivered at least some answers, he said.<\/p>\n<p>&#8220;It gives us a lot of confidence that when we&#8217;re repairing things which are in the plant, and putting things back, that they weren&#8217;t the primary factor.<\/p>\n<p>&#8220;We can now press ahead and figure out what the design solution needs to be.&#8221;<\/p>\n<p>But other potential causes were yet to be ruled out, he said.<\/p>\n<p>More funding for plant repair<\/p>\n<p>Mayor Andrew Little said Wellington City Council&#8217;s capital funding for Wellington Water has been underspent by $15 million this financial year.<\/p>\n<p>Given the urgency of the repairs, the council gave Wellington Water consent to draw down between $8 and $9 million of that to immediately order the new control systems it needed, Little said.<\/p>\n<p>&#8220;That should expedite the repair and reinstatement of the plant.&#8221;<\/p>\n<p>The mayor&#8217;s office later said the underspend came from a range of things.<\/p>\n<p>&#8220;Wellington Water are always looking to achieve value for money, which can generate savings (for example on tenders) which adds to &#8216;underspend&#8217; in the current financial year.<\/p>\n<p>&#8220;Some projects occur over multiple years. When projects take longer than anticipated, some spending moves to future financial years, which creates underspends in the current year.&#8221;<\/p>\n<p>Little emphasised the report released today was helpful in identifying a possible cause, but was not conclusive.<\/p>\n<p>More reports would follow including expert modelling done in London, Little said.<\/p>\n<p>Report suggestions<\/p>\n<p>The experts suggested Wellington Water install additional air release equipment at specific locations in the system.<\/p>\n<p>&#8220;This is expected to provide some improvement to the issues identified until the design of a new bypass pipeline alignment and connection can be developed and implemented.&#8221;<\/p>\n<p>The report was just one piece of the puzzle, Little said.<\/p>\n<p>&#8220;There are other areas of interest that require a more detailed investigation, and Wellington Water has commissioned an external specialist to conduct a wider investigation into these other factors.<\/p>\n<p>&#8220;It&#8217;s natural to want a quick answer, but it&#8217;s important that we take the time to uncover all the facts and not draw conclusions too early.<\/p>\n<p>&#8220;Wellingtonians deserve assurance that our recovery addresses the root cause and any related factors, so we can be confident we&#8217;re preventing this from happening again.&#8221;<\/p>\n<p><img decoding=\"async\" loading=\"lazy\" src=\"https:\/\/www.newsbeep.com\/nz\/wp-content\/uploads\/2026\/02\/4JTQ53B_Image_1_jpg.jpeg\" width=\"1050\" height=\"700\" alt=\"Untreated water is leaking onto the capital's south coast beaches due to the Moa Point Treatment Plant flooding and being turned off from early this morning.\"\/><\/p>\n<p class=\"photo-captioned__information\">\nThe Wellington plant failed last month, flooding the facility and sending millions of litres of raw sewage into the sea each day.<br \/>\nPhoto: RNZ \/ Samuel Rillstone\n<\/p>\n<p>Air pocket &#8216;burping&#8217; seen since<\/p>\n<p>The report revealed that Veolia, the plant operator, told Wellington Water at a meeting this week that crews had observed the burping of air pockets during the storm on 3 March when there was a high level of water running through the system.<\/p>\n<p>&#8220;The operator &#8230; observed burping of large air pockets and large splashes from the outlet chamber during the initial pumping sequences,&#8221; it said.<\/p>\n<p>That showed the air release capacity of a vent pipe downstream had been exceeded at times, the report said.<\/p>\n<p>More risks identified<\/p>\n<p>The experts identified other potential risks at the plant and made a number of technical recommendations.<\/p>\n<p>&#8220;Wellington Water should address the potential risk of a blockage or debris in the outfall section of the pipe and implement monitoring of operating pressures in the ocean outfall (during the recovery phase at a minimum).&#8221;<\/p>\n<p>The company should also review the condition of existing air and isolation valves, and replace them if necessary, the report said.<\/p>\n<p>CCTV from the pipeline showed the polyurethane liner had eroded and cement mortar had potentially degraded in some sections, it said.<\/p>\n<p>&#8220;This has occurred due to high velocity super-critical (shallow and fast) flow impacting on the liner.<\/p>\n<p>&#8220;This flow regime presents risks to the long-term durability of the effluent pipeline liner and structural steel which warrants additional review and investigation.&#8221;<\/p>\n<p>An independent Crown review into the failure is also underway, and its final report is expected in August.<\/p>\n<p><a href=\"https:\/\/radionz.us6.list-manage.com\/subscribe?u=211a938dcf3e634ba2427dde9&amp;id=b3d362e693\" rel=\"nofollow noopener\" target=\"_blank\">Sign up for Ng\u0101 Pitopito K\u014drero<\/a>, a daily newsletter curated by our editors and delivered straight to your inbox every weekday.<\/p>\n","protected":false},"excerpt":{"rendered":"The catastrophic failure of the Moa Point wastewater treatment plant may have been caused by air trapped in&hellip;\n","protected":false},"author":2,"featured_media":343703,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[22],"tags":[48,47,273,111,43,139,69,49,46,44,45,147],"class_list":["post-343702","post","type-post","status-publish","format-standard","has-post-thumbnail","category-environment","tag-audio","tag-current-affairs","tag-environment","tag-new-zealand","tag-news","tag-newzealand","tag-nz","tag-podcasts","tag-public-radio","tag-radio-new-zealand","tag-rnz","tag-science"],"_links":{"self":[{"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/posts\/343702","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/comments?post=343702"}],"version-history":[{"count":0,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/posts\/343702\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/media\/343703"}],"wp:attachment":[{"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/media?parent=343702"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/categories?post=343702"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.newsbeep.com\/nz\/wp-json\/wp\/v2\/tags?post=343702"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}