San Francisco’s third and final weekend closure tied to the 19th Avenue rehabilitation project ended Monday morning, which Caltrans said was ahead of schedule.
The 75-hour closure completed work, with all lanes reopening around 6 a.m., on northbound and southbound lanes along a stretch of 19th Avenue, or state Highway 1, between Holloway Avenue and Sloat Boulevard.
Caltrans said in a statement that crews repaved all northbound and southbound lanes between Lincoln Way and Holloway Avenue, totaling about 18.8 lane miles.
The California Street intersection will be paved later this summer, and the project also includes upgrades to the traffic detection system.
Caltrans said organizing the work into three weekend closures reduced public disruption from 40 days to 10 days.
According to the state agency, final striping work is scheduled during nighttime hours this week, with more electrical work planned in June that is not expected to significantly affect travel or nearby residents.