The planned rebuild of the Palisades Recreation Center is expected to take 15 to 18 months once construction begins and cost between $45 to $50 million, according to information shared on Tuesday evening at a meeting of the Park Advisory Board held in Rustic Canyon.
Nick Geller, managing director of Steadfast LA, delivered the updates. Steadfast LA is part of a public-private partnership leading the effort to rebuild the recreation center alongside the nonprofit LA Strong Sports and the City of Los Angeles.
While there is no set start date for construction on the project, Geller said building permits will likely be obtained in August. The final construction timeline will be shared with the community once those permits are secured.
An internal landscape plan is expected to be delivered to Steadfast LA within the next three to four weeks, which will then be presented to both the PAB and the local community.
Geller noted that while the team hopes to complete the overall project within 15 months, potential weather and supply delays could push the timeline to 18 months. However, crew members will prioritize certain elements of the construction to minimize disruptions to local sports.
“As an example, we’re going to try to get the baseball fields rebuilt so that PPBA can have their…season there in March 2027,” Geller said. “We expect the baseball field to be up and running while we are working on the rest of the park.”
Geller also addressed ongoing community concerns regarding project finances and potential commercialization, emphasizing that the partnership’s role is strictly limited to the construction phase.
“The public-private partnership is for the development of the improvements of the park,” Geller said. “Once we are completed with our scope of this project, we donate it back to the City of L.A., and the city continues to run the park as it was prior to the fire. There’s no private element to this. Nobody’s making money. There’s no privatization.”
L.A. Department of Recreation and Parks Senior Facility Director Jasmine Dowlatshahi and Mike Tomas of the Palisades Tennis Center reported that the reconstruction of the fire-damaged tennis courts is progressing.
According to Dowlatshahi, a lack of on-site staff at the recreation center has caused some administrative hurdles, but the restoration of several tennis courts is nearing completion.
“Courts five through eight should be opening up soon,” Dowlatshahi said. “We’re just waiting to get the green light.”
Tomas noted that the City of Los Angeles is directly handling the court reconstruction, which includes resurfacing and new fencing. Though no firm reopening date has been set, Tomas said he hopes the courts will be ready for use before Palisades Charter High School begins its fall semester.
In the meantime, Dowlatshahi reported that several recreational programs have been temporarily relocated to Rustic Canyon Park and Penmar Park. Displaced activities include local basketball leagues, flag football, senior kickball and crocheting classes.
The PAB meeting also featured updates from Council District 11 Field Deputy Arus Grigoryan, who touched on several local park developments. According to Grigoryan, a fencing restoration project at George Wolfberg Park will be discussed at the Board of Recreation and Parks Commissioners meeting on Thursday, July 16, at 9:30 a.m. at the Ramona Hall Community Center. Grigoryan added that a new, long-term capital improvement project has been launched to rehabilitate the Temescal Pumping Plant and restore the water pump on Temescal Canyon Road.
The meeting ended with a discussion on the long-delayed Potrero Canyon Lateral Trail. PAB member Rob Weber urged the board to pressure Caltrans for an access easement over its maintenance yard, noting that while $1.5 million in funding has been secured, the project remains stalled by access disputes.
“This has been talked about for at least 10 years,” Weber said. “To hear that Bureau of Engineering is still talking with Caltrans about getting access over a portion of the Caltrans yard to make a route for the trail is completely unacceptable.”
A virtual community meeting regarding the Potrero Canyon Bridge Project is scheduled for Thursday, July 16, at 5:30 p.m. For more information and to register for the meeting, click here.