10 Mile Road

Over the Rouge River east of Middlebelt Road in Farmington Hills. Replace culvert, asphalt paving in the vicinity of the culvert, removal of boardwalk, sidewalk improvements, new signage and pavement markings. Detour is Middlebelt Road to 11 Mile Road to Inkster Road back to 10 Mile Road and vice versa. Projected completion in October.

 

12 Mile Road

East of Orchard Lake Road to Autumn Ridge in Farmington Hills. Remove existing pavement, adding asphalt paving, reconstruction of select sidestreet approaches, ADA-compliant crosswalks, traffic signal modernization at the 12 Mile/Middlebelt intersection and upgrading SMART bus stops. One lane is maintained in each direction on 12 Mile Road for business and residential access. Projected completion in early September.

 

12 Mile Road

From Novi Road to Farmington Road in Farmington Hills and Novi. PHASE 1 –  Drake Road to Farmington Road and Novi Road to Haggerty Road to remove existing pavement, adding asphalt paving, concrete patching on 12 Mile west of M-5 to Novi Road, ADAcompliant crosswalks/pedestrian signals, SMART bus stop upgrades and repairs to curbs and gutters. One lane maintained in each direction on 12 Mile Road for business and residential access. Projected  completion in late Fall.

 

14 Mile Road

From M-5 to East Lake Drive/East Walled Lake Drive in Commerce Township, Novi and Walled Lake. Great Lakes Water Authority water main replacement. Eastbound 14 Mile Road closed with a detour. Westbound 14 Mile Road is mostly open to traffic with periodic closures. Projected completion is late July.

 

Dixboro Road

Between 9 Mile Road and 10 Mile Road in South Lyon and Green Oak Township. A private developer will pave a section of the gravel road, from 10 Mile Road to Londonderry Drive. The road is closed with residential access on Dixboro Road. Detour is 10 Mile Road to Rushton Road to 9 Mile Road, back to Dixboro Road. Projected completion is Aug. 21.

 

Fagan Road

Over the Swartz Creek tributary between Grange Hall Road and Lahring Road in Holly Township, just north of Shields Road. Residential access on both sides of the closure. Road closure due to a deteriorating culvert. Replacement plans will be announced in 2027. Detour is Quick Road to North Holly Road to Lahring Road, back to Fagan Road and vice versa. Projected completion in 2027.

 

Greenfield Road

North of Lincoln to 12 Mile Road in Berkley, Oak Park and Southfield to remove existing pavement, asphalt paving, reconstructing select sidestreet approaches, ADA-compliant crosswalks, curb/gutter repairs, upgrading SMART bus stops and modernizing traffic signals on Greenfield Road at the Kroger entrance, 11 Mile Road and Catalpa. One lane open in each direction on Greenfield Road for business access. Projected completion is early September.

 

9 Mile Road

Gravel road paving by a private developer on 9 Mile Road in Lyon Township. Road  closed east of Addison Boulevard. to Briar Meadow Drive. Residential access maintained within the closure. Detour is Griswold Road to 10 Mile Road to Currie Road back to 9 Mile Road and vice versa.

Novi Road

Between 8 Mile Road and 9 Mile Road to remove  existing pavement, asphalt paving, adding continuous center left turn lane, adding two NB lanes and one SB lane from the Rouge River/Allen Drive to 9 Mile, drainage improvements, reconstructing side-street/driveway approaches and ADA-compliant crosswalks. Northbound Novi Road closed; southbound Novi Road remains open for residential and business access. Northbound Novi Road detour is 8 Mile Road to Beck Road to 10 Mile Road back to Novi Road. Projected completion is late summer.

 

Pontiac Trail/Lafayette Street

9 Mile Road to the CSX tracks, north of 10 Mile Road in Lyon Township. and South Lyon for road reconstruction, asphalt paving, drainage improvements, traffic signal upgrades, extending the SB right turn lane on 9 Mile from Princeton, adding an EB right-turn lane on 9 Mile at Pontiac Trail and ADA-compliant crosswalks. Northbound Pontiac Trail/Lafayette Street closed to traffic; southbound remains mostly open. On-street parking is prohibited. Business and sidewalk access maintained. Northbound detour is 9 Mile Road to Griswold Road to 10 Mile Road to Martindale Road to 11 Mile Road back to Pontiac Trail. There will be additional road closures; dates and detours will be announced. Projected completion is mid-November.

 

New roundabout

Intersection for Wixom Road, Wixom Trail, Duck Lake Road and Sleeth Road closed in Commerce Township and Milford Township for roundabout construction, asphalt paving, storm sewer installation, public lighting at the intersection, ADAcompliant pedestrian crosswalk on the east leg of the roundabout and new curbs and gutters. Detour is Glengary Road to Benstein Road to Sleeth Road to North Commerce Road to East Commerce Road and vice versa. Projected completion is Sept. 4.

 

M-53

In Macomb County, southbound M-53 will be closed from 30 Mile to 32 Mile Road from 10 a.m. Wednesday until Aug. 19 for underground work by Washington Township.

I-94

In Macomb County, westbound I-94 will be closed from Metropolitan Parkway to M-3/Gratiot including all ramps until 5 a.m. Monday for road work.

In Wayne County, eastbound I-94 will have one lane open from Beaubien to Russell from 7 a.m.-3 p.m. Saturday for bridge work.

In Wayne County, Livernois ramp to eastbound I-94 will be closed through Aug. 9.

Wayne Road ramp to westbound I-94 will be closed until 2027.

 

I-75

In Oakland County, northbound and southbound M-1/I-75BL/Woodward will be closed from South Boulevard to Rapid Street until 9 a.m. Sunday for local event.

In Oakland County, northbound M-1/I-75BL/Woodward will have one lane open until 9 a.m. Sunday for local event.

In Oakland County, southbound M-1/I-75BL/Woodward will have one lane open from M-59 to Rapid Street until 9 a.m. Sunday for local event.

In Oakland County, northbound I-75 will have one lane open from 8 Mile Road to I-696 including 9 Mile ramp to northbound I-75 ramp closed until 8 p.m. Sunday for bridge work.

In Wayne County, southbound I-75 will have one lane open from Schaefer to M-39/Southfield from 7 a.m. Saturday to 7 p.m. Sunday, including the Schaefer ramp to southbound I-75 and southbound I-75 ramp to and from Outer Drive for road treatment.

In Wayne County, northbound and southbound I-75 from Schaefer to Springwells  will have one lane open with moving lane closures overnight from 9 p.m. Monday until 4 a.m. Tuesday.

M-10

In Oakland County, northbound M-10 at 9 Mile Road will have one lane open from 10 a.m.-2 p.m. Monday for bridge work.

In Wayne County, northbound M-10 will be closed at Forest Avenue including M-5/Grand River ramp to northbound M-10 until 5 a.m. Monday for bridge work.

In Wayne County, southbound M-10 at West Grand Boulevard will have one lane open from 9 a.m.-3 p.m. Saturday for road work.

 

M-14

In Wayne County, northbound and southbound Sheldon is closed under M-14 until 5 a.m. Monday for bridge work.

Sheldon ramp to westbound M-14 will be closed until late fall.

 

M-15

In Oakland County, northbound M-15 will be closed with flag control from Oakwood to Ray Road/County Line from 7 a.m. Monday until 5 p.m. Wednesday for paving.

 

M-39 (Southfield)

In Wayne County, Van Born ramp to southbound M-39 will be closed from 7 a.m. Monday until 3 p.m. Friday.

 

US-24 (Telegraph)

In Oakland County, southbound US-24 will have two lanes open nightly from M-10 to M-102/8Mile Road until 5 a.m. Wednesday for road work.