$1.9 million effort replaced more than 42,000 square feet of damaged sidewalks at over 250 locations in Mira Mesa and University City.

SAN DIEGO — Fresh concrete is creating safer pathways for people across Mira Mesa and University City as the City of San Diego nears completion of what officials say is the largest sidewalk replacement project ever completed by its in-house construction crews.

The $1.9 million project replaced damaged sidewalk panels at more than 250 locations throughout Council District 6, totaling roughly 42,000 square feet of new concrete. Crews have spent the past several months repairing aging sidewalks throughout the two communities, including work along Black Mountain Road in Mira Mesa.



This story continues below.

City officials say the project stands out not only because of its size, but because it was completed by city employees rather than outside contractors.

“This is close to a $2 million dollar project that we were able to mobilize in a record nine months,” said Naomi Chavez, interim director of the City’s Transportation Department. “Typically this type of project takes two-and-a-half years from the beginning of project creation to contracting out to completion.”

According to the city, a project of this scale would normally require a lengthy competitive bidding process and construction schedule. By keeping the work in-house, city engineers and construction crews were able to move the project from planning to near completion in less than a year.

“Anytime the work is performed in-house, it tends to be a little faster,” Chavez said. “With the contracting out, there’s a lot of the decisions and administrative back and forth that happens. We have a little bit more control with the project by keeping it in-house.”

The repairs address a long-standing concern for many residents. Damaged sidewalks are among the most frequently reported issues through the city’s Get It Done system, according to Councilmember Kent Lee, who represents District 6.

“It’s one of the most commonly reported items in the city on Get It Done,” Councilmember Lee said. “There are many sidewalks throughout the city that still need repair.”

Councilmember Lee said deteriorating sidewalks can create safety hazards for pedestrians and increase liability costs for taxpayers.

“We get folks who are tripping on damaged sidewalks, trees that are lifting pieces up,” Councilmember Lee said. “We often see repairs get done, but that’s not the same as actually fixing the entire piece of sidewalk.”

City leaders say the newly installed sidewalks will improve accessibility and walkability for residents of all ages, including families with strollers, seniors and people with mobility challenges.

“Sidewalk replacements are very important citywide,” Chavez said. “It decreases liability for trip-and-falls. It just makes communities a lot more walkable, whether we have folks pushing strollers, walking, riding tricycles.”

The project is now nearing completion, with crews putting the finishing touches on new sidewalks throughout Mira Mesa and University City. City officials say the effort could serve as a model for completing future infrastructure projects more quickly by utilizing in-house crews whenever possible.