One of Winter Park’s main thoroughfares is getting an overhaul starting Jan. 20. The Park Avenue Refresh project serves several purposes, said Clarissa Howard, city of Winter Park communications director.

“The last time Park Avenue was renovated or any significant work done was back in 1996 to 1999, when it was streetscaped with the bricks,” Howard said. “That infrastructure has definitely degraded in the past 30 years. So we’re pulling in all new conduit for electric, fiber, irrigation and low voltage.”

The Park Avenue refresh will include updated planters, bollards and 110 new light poles that were custom-made for this project. (COURTESY OF CITY OF WINTER PARK)

The infrastructure improvements will be paired with new street lights, trash and recycling canisters, signage, and architectural elements that will be consistent throughout the district. Broken sidewalks will be repaired, and many intersections will receive bump-outs and bollards to improve pedestrian safety.

Howard said that many of the elements in the refresh plan came from a survey of residents and businesses, along with public meetings and work sessions to solicit feedback.

“We have gone in front of the [Winter Park] commission four or five times now, and every single commission meeting has had public input,” Howard said. “On a monthly basis, I meet with the Park Avenue District and give them an update of where we are.” 

Along with her communications role, Howard is serving as the project manager for the refresh, working with consultants Alex Stringfellow of Stringfellow Urban Planning & Design and Mike Lewis, general contractor at Ovation Construction. 

Phase 2 of the project is scheduled to begin in January 2027 and will affect Park Avenue between Garfield and New England avenues, which includes Central Park on the west side. Construction on the last phase, between New England and Fairbanks avenues, is expected to start in January 2028.

Some Park Avenue improvements happened in September 2025. Gateway signs were added by Webster and Fairbanks avenues. (NICK GEORGOUDIOU)

Howard said that the scheduling is strategic, starting with the part of Park Avenue with the fewest homes and businesses.

“Phase 1 is actually the largest as far as length,” Howard said. “It gives us that test of commercial, but not a full stretch of commercial. That’ll give us a good example of what Phase 2 is going to look like for all those businesses.”