The Old Jacksonville Highway widening is delayed to 2030 due to right-of-way and utility challenges, impacting local traffic and development plans.
TYLER, Texas — The start of construction on Old Jacksonville Highway has been delayed until at least 2030.
The Tyler Area Metropolitan Planning Organization (MPO) hosted a public meeting Monday to discuss the delayed construction start on the widening of FM 2493, or Old Jacksonville Highway, from 2028 to 2030. Members of the public came and went from 4 to 5 p.m. at the Tyler Development Center downtown to hear updates from MPO Director Michael Howell and ask questions about the project.
“The reason for that delay is to accommodate the time needed to acquire a right-of-way along the corridors and to be able to move the utilities that are needed before the construction can begin,” Howell said.