PennDOT will institute a single-lane restriction on the Parkway East on Monday night as the agency continues maintenance related to the Commercial Street Bridge replacement project.
I-376 will be restricted eastbound between the Squirrel Hill/Homestead interchange (Exit 74) and the Edgewood/Swissvale interchange (Exit 77) beginning at 9 p.m. on Monday and through 5 a.m. on Tuesday.
Workers will conduct concrete pouring operations.
Workers successfully replaced the Commercial Street Bridge over the summerusing a lateral slide maneuver and a system of hydraulic jacks. The bridge was fully closed to traffic for 17 days but reopened one week ahead of schedule.
However, PennDOT expects wrap-up work on the $95 million project to stretch into next summer. The agency is simultaneously working on the $100 million Parkway East Betterment Project to extend the life of the roadway and its more than 20 supporting bridges.