Pennsylvania Gov. Josh Shapiro signs an executive order on Aug. 18, 2026, establishing stricter “guardrails” for data centers. (Commonwealth Media Services)
With a few dozen data centers already up and running in Pennsylvania and proposals on the table for over 100 more, public opposition is growing — especially to the new hyperscale projects intended to support AI. Like his counterparts across the Chesapeake Bay region, Gov. Josh Shapiro is reading the room.
According to a Quinnipiac University poll released in July, 74% of Pennsylvania voters say they would be against building an AI data center in their community. And on Aug. 18, Shapiro signed an executive order intended to give municipalities more control over data center development and to establish stricter guardrails for those projects. Governors in Maryland and Virginia have since followed suit.
Shapiro’s order is “an important way to address concerns about consumer impacts, environmental impacts and public health impacts from data centers,” said Robert Routh, the state’s policy director for the Natural Resources Defense Council.
Shapiro, a Democrat, was once a champion for data center development. In June 2025, his administration announced a $20 billion Amazon investment for AI infrastructure in Pennsylvania. “Our team worked closely with local leaders and Amazon to land this deal,” he said at the time.
But with public outcry growing and the number of proposals multiplying, the Shapiro administration is attempting to place checks on the industry. In a May 2026 precursor to the executive order, Shapiro’s team announced the Governor’s Responsible Infrastructure Development (GRID) initiative, intended to establish “strict standards that data centers must comply with to receive support from the commonwealth.”
Those standards include commitments to economic development, energy affordability and transparency. They also address environmental protection, such as requirements for technologies that minimize water use and air pollution. In exchange, data center developers could expect speedier permitting through the PA Permit Fast Track Program.
But compliance with GRID is voluntary. The new executive order adds teeth to the program and gives more power to local communities.
Now, developers who sign a legally binding agreement with the state Department of Environmental Protection to meet GRID requirements can immediately submit permit applications for review. But DEP will not issue those permits until municipalities have approved the project.
If a developer refuses to sign the agreement, DEP will not even begin reviewing its permit applications until local approval is secured. And the department will not issue any permits until all applications have been submitted. Developers who do not agree to GRID will also not qualify for the existing tax exemption on data center computer equipment.
Want to dive deeper?
Learn more about how data centers impact the environment with the Bay Journal’s free downloadable backgrounders.
The order also removes all data center proposals from the PA Permit Fast Track Program, prohibits developers from using nondisclosure agreements and requires data center operators to report energy and water usage to DEP annually beginning in July 2027.
“There are no AI data centers up-and-running right now in Pennsylvania,” Shapiro remarked at his executive order signing ceremony. And only two have completed DEP review, according to the department’s new Data Center Permit Tracker website. One of those is in Westmoreland County, and the other is one of two planned for Lancaster County.
The expectation, one administration official said on background, is that these new requirements will help distinguish projects that may never be built from “projects that are serious, have financing and access to power and have a committed end user.”
The order means that developers cannot use the state’s approval as leverage at the local level, said David Sanko, executive director of the Pennsylvania State Association of Township Supervisors. Developers, he adds, will no longer get their state permits first and then say, “Well, the state already says ‘okay.’ Why are you in the way?”
Kirk Stoner, director of planning for Cumberland County, across the Susquehanna River west of Harrisburg, wishes the GRID guidance had come sooner. His county is home to the hotly contested $15 billion PAX-1 data center project in Middlesex Township. Some of the arguments over energy, water and air quality could have been more focused if there had been more definitive information on resource impacts to consider upfront, he said.
But exactly how the executive order will play out in individual towns isn’t yet clear. “A lot of the ordinances that I’m seeing here in Cumberland County are really strict, and I’m not sure that there’s going to be a lot of projects moving forward to the state level,” Stoner said.
A municipality might, for example, restrict data center development to a minimum lot size of 40 acres within an industrial zone that doesn’t contain available lots that size. Stoner said it begs the question, “At what point does the private sector and the data center industry start to push back on some of those and come in and challenge ordinances to say they’re exclusionary?”
Stoner also wonders whether some municipalities might actually request that DEP complete reviews of environmental permits first, so they don’t waste time and concern citizens with projects that might ultimately be killed at the state level.
Another question is how many data center developers will sign the GRID agreement.
“In distinguishing speculative proposals from real projects, it’s important that rules are not changed midstream, impacting ongoing investment in verified and responsible data center projects,” said Dan Diorio, executive vice president of state policy and government affairs for the Data Center Coalition, a trade association. “Companies have made plans, [and] communities have prepared for economic opportunities.”
As of September 18, one month after the executive order was signed, a Shapiro administration official told the Bay Journal thatno data center developers had signed on.
Sanko, of the township supervisors association, expects that data center developers will dedicate time and attorney fees to understanding exactly what the order means before signing. He predicts none will openly refuse to sign before election day.
The upcoming November gubernatorial election is a reminder that executive orders come and go with administrations.
There are more than a dozen bills now pending in the Pennsylvania legislature that would add protections for communities considering data center proposals, said Michael Helbing, executive director of Penn State’s Center for Energy Law and Policy.
One such bill, HB 2650, would incentivize compliance with GRID by only offering the existing tax breaks on data center computer equipment to those who follow the initiative’s standards. The bill passed the state house in June 2026 but has not been brought to a vote in the senate.
Shapiro took “a critical step forward,” but this does not mean “mission accomplished,” said Routh of the Natural Resources Defense Council. “If we want binding requirements on data center projects, [GRID] has to have the full force of law behind it, which requires legislation.”