Read about some of the latest updates on road and capital projects in League City. This list is not comprehensive.

Ongoing project

League City Parkway right turn lane

Project: An eastbound right-turn lane will be designed west of Butler Road to west of the I-45 southbound frontage road, and tie to the Texas Department of Transportation’s right-turn lane.

Update: Construction is ongoing.

Timeline: anticipated completion by end of MarchCost: $2.08 millionFunding source: Galveston County bond fundsUpcoming projects

Extension of Hobbs Road to FM 517

Project:

Approximately 1,880 feet of four-lane divided urban roadway will be constructed from the existing terminus south of the intersection of Patagonia Street and Hobbs Road to FM 517.

Update: The project plans are near completion, and are currently in right-of-way acquisition and TxDOT permitting phase, which will take the next several months.

Timeline: anticipated bid date by late summer, pending ROW acquisition, with construction starting as early as late fall 2026 or early 2027Cost: $7.7 millionFunding source: Galveston County and city fundsFM 518 at Bay Area Boulevard intersection improvements

Project:

To improve intersection capacity and safety, the project scope includes adding a long southbound right-turn lane and extending the existing northbound left-turn lane from 135 feet to 350 feet.

Update: Project plans are in review, with bidding beginning in the summer.

Timeline: construction slated to start in late fall or early 2027Cost: $628,428Funding source: city cash funds