Hays County drivers can track progress on six transportation projects—ranging from new deceleration lanes and neighborhood street upgrades to multimillion-dollar widening and extension work.

Upcoming projects

RM 967 deceleration lanes

Project: deceleration lanes added in two locations:

Garlic Creek Drive at Remuda TrailGarlic Creek Drive at Grove LaneUpdate: in final construction plansTimeline: 2021-TBDCost: $2.57 millionFunding source: 2021 Buda bondAustin Street reconstruction

Project: parking, sidewalks and stormwater improvements FM 2770 to San Antonio Street

Update: at 60% design phase

Timeline: 2021-TBDCost: $8.6 millionFunding source: 2021 Buda bondBishop and Belvin Street improvements

Project: full-depth road reconstruction with drainage, water, wastewater, retaining walls and sidewalk improvements from Belvin Street to West San Antonio Street

Update: at 90% design phase; acquisition process underway

Timeline: 2026-28Cost: $11.26 millionFunding source: Capital Improvement Program; city utility and general fundsOngoing projects

Kyle Parkway-Lehman Road extension

Project: Lehman Road extended into a four-lane roadway from Bunton Creek Road to Dacy Lane; Kyle Parkway to connect with the new segment

Update: at 95% design phase

Timeline: 2023-27Cost: $42.5 millionFunding source: 2022 Kyle bondOld Bastrop Road widening

Project: from Rattler Road to Centerpoint Road

Update: water main installed in September; waterline crossing underway

Timeline: 2025-26Cost: TBDFunding source: 2025 road project certificates of obligationOld Stagecoach Road widening and Center Street improvements

Project: Old Stagecoach Road widened to a four-lane roadway from Veterans Drive to Main Street. Work completed in four parts:

north portion of Old Stagecoach Road from Veterans Drive to Six Creeks BoulevardOld Stagecoach Road from Six Creeks Boulevard to Center StreetCenter Street from Old Stagecoach Road to Veterans Drivethree lanes from Veterans Drive to Main StreetUpdate: in final design phaseTimeline: 2023-27Cost: $41.2 millionFunding source: 2022 Kyle bond

“>