Read about some of the latest updates on road and capital projects in League City. This list is not comprehensive.
Ongoing projects
Reconstruction of Butler Road and Turner Street
Project: The project is being carried out in two phases and involves roadway improvements and reconstructing the asphalt roadway, as well as waterline work.
Update: Work is currently ongoing.
Timeline: project expected to be done by end of October 2026Cost: $6.12MFunding source: city’s reinvestment fundFM 518 at County Lane intersection improvements
Project:
The project includes replacing the area’s span wire traffic signals with signals on poles, as well as improving the pedestrian crossing bridge and making the area’s signals more resilient to storms.
Update: The project was awarded in August 2025.
Timeline: contract calls for 320 days to complete, with work expected to wrap in fall 2026 due to long wait on signal equipmentCost: $504,000Funding source: city’s reinvestment fundUpcoming project
League City Parkway and Walker Street intersection improvements
Project: Work includes a redesign of the intersection to add additional lanes and adjust drainage.
Update: Permitting from the Texas Department of Transportation is pending.
Timeline: bidding to now come in later 2026Cost: $2.1MFunding source: Galveston County’s 2018 bond
“>