Road projects are moving forward in the Schertz, Cibolo, Live Oak and Selma areas as I-35 construction changes driving patterns. Learn more about three road project updates.

I-35 NEX Central

Project: The 9.5-mile project includes three elevated lanes, comprising two main lanes and one high-occupancy vehicle lane for both northbound and southbound directions. The elevated lanes will provide direct connections to Loop 410 North and Loop 1604 West.

Update: On Feb. 15, all lanes of eastbound Loop 1604 from Nacogdoches Road to IKEA-RBFCU Parkway were set to a new traffic pattern. The eastbound Loop 1604 mainlanes will be temporarily detoured to the eastbound bypass ramp east of Nacogdoches Road, then realigned to the eastbound Loop 1604 mainlanes at IKEA-RBFCU Parkway.

Timeline: June 2022-fall 2027Cost: $1.5 billionFunding source: Texas Department of TransportationFM 1103

Project: Work on this project will consist of the expansion of the roadway from two lanes to four lanes, with a raised median or continuous left-turn lane, bike lanes and sidewalks.

Update: Traffic on FM 1103 was shifted in February, initiating the third phase of the project. Construction is underway on the southbound lanes, while the northbound lanes were restriped to accommodate one lane of traffic in each direction. Drivers should anticipate delays and are encouraged to allow extra travel time or use alternate routes when possible.

Timeline: November 2022-2030Cost: $39.29 millionFunding sources: TxDOT, city of Cibolo, city of SchertzCibolo FY25 Street Rehabilitation Package II

Project: Work includes the reconstruction of Firebird Run, Silver Wing and Town Creek Road. This is the second set of roads funded for reconstruction under the 2025 general obligation bonds. The first phase included construction on Deer Creek Boulevard and Green Valley Road.

Update: Work on Town Creek Road is expected to wrap up by the end of February. Construction on Firebird Run began Jan. 8 and is expected to be completed in the spring. City Manager Wayne Reed on Feb. 10 said the first layer of asphalt will be placed on Firebird Run by Feb. 23.

Timeline: September 2025-spring 2026Cost: $3.1 millionFunding source: city of Cibolo fiscal year 2025 certificate of obligation bonds

“>