Grapevine High School will see substantial renovations over the summer breaks of 2026 and 2027 as part of the Grapevine-Colleyville ISD’s 2024 bond program approved by voters.
District trustees approved a maximum $14.4 million contract to Lee Lewis Construction Inc. at their Feb. 23 regular meeting. Major items include roofing and kitchen work. Lee Lewis is the construction manager on the project.
Paula Barbaroux, the district’s chief operations officer, told trustees the project is coming in substantially under budget. However, she said, indications are that other projected budgets for work to be done under the 2024 bond will be over budget.
“Kind of building up the chips there,” she said.
Lee Lewis received 53 bids for work to be done in 26 trades on the Grapevine High School project, and determined they were qualified, Barbaroux said.
“That was pretty robust coverage and competition there,” she said.
The work will be done during the summers to ensure no disruption to the school, she said. Estimated completion is Aug. 1, 2027, she said.
“They’re not going to be doing renovations at Grapevine High School while school is in session,” she said.
To learn more about how the transcript that informed this report was created, visit covergov.com.
Scott Nishimura is senior editor at the Fort Worth Report. If you believe anything in this account is inaccurate, please email us at news@fortworthreport.org with “Correction Request” in the subject line.
This <a target=”_blank” href=”https://fortworthreport.org/2026/03/07/grapevine-high-school-renovations-set-for-next-two-summers/”>article</a> first appeared on <a target=”_blank” href=”https://fortworthreport.org”>Fort Worth Report</a> and is republished here under a <a target=”_blank” href=”https://creativecommons.org/licenses/by-nd/4.0/”>Creative Commons Attribution-NoDerivatives 4.0 International License</a>.<img src=”https://i0.wp.com/fortworthreport.org/wp-content/uploads/2021/04/cropped-favicon.png?resize=150%2C150&quality=80&ssl=1″ style=”width:1em;height:1em;margin-left:10px;”>
<img id=”republication-tracker-tool-source” src=”https://fortworthreport.org/?republication-pixel=true&post=436530&ga4=2820184429″ style=”width:1px;height:1px;”><script> PARSELY = { autotrack: false, onload: function() { PARSELY.beacon.trackPageView({ url: “https://fortworthreport.org/2026/03/07/grapevine-high-school-renovations-set-for-next-two-summers/”, urlref: window.location.href }); } } </script> <script id=”parsely-cfg” src=”//cdn.parsely.com/keys/fortworthreport.org/p.js”></script>