EL PASO, Texas (KFOX14/CBS4) — View the interactive TxDOT map and cameras here.
I -10 widening west closures
Phase 1
Monday, April 20 – Saturday, April 25 (As Needed)
Daily, 9 a.m. – 4 p.m.
Nightly, 9 p.m. – 6 a.m.
I-10 east and westbound between Vinton and Reler alternate lane closuresNorth and South Desert between Vinton and Resler alternate lane closures
Crews will be working on punch list items.
Phase 2
Friday, April 17 (EMERGENCY CLOSURE)
9 a.m. – 4 p.m.
Full roadway closure of South Desert Boulevard between Valley Chile Road and Marne Road.
(Valley Chile entrance ramp at I-10 eastbound will remain open).
Crews will be re-setting concrete barriers and performing work zone traffic pavement markings.
Tuesday, April 21 (FULL CLOSURE)
9 a.m. – 4 p.m.
North Desert between I-10 westbound Transmountain entrance ramp and Vinton exit ramp closedDetour: Take I-10 westbound Transmountain entrance ramp, exit at Vinton.
Crews will be moving concrete traffic barriers and guardrail repairs.
(48-HR FULL CLOSURE)
Saturday, April 25 – Monday, April 27
3 a.m.- 3 a.m.
I-10 eastbound between Anthony, New Mexico, and Los Mochis closed
Detour: Traffic will exit at 404, take 404 to 460 to Doniphan, turn left on Vinton, turn right on South Desert, and enter I-10 eastbound at the Los Mochis entrance ramp.
Crews will be conducting a traffic switch. Once closure lifts. Exit 1, 2 and the EB entrance ramp to I-10 will be closed. Drivers should use EB Exit 0 for access between Anthony and Vinton.
Monday, April 20 – Saturday, April 25 (As Needed)
9 a.m. – 4 p.m. & 9 p.m. – 6 a.m.
I-10 east and westbound between Anthony and Nashua alternate lane closures (No Detour Needed)North and South Desert between Anthony and Nashua alternate lane closures (No Detour Needed)
Crews will be conducting dirt work hauling.
Monday, April 20 – Saturday, April 25 (As Needed)
9 a.m. – 4 p.m.
I-10 east and westbound Bypass between Redd and Mesa closed
Detour: Continue South/North Desert.
Crews will be working on ornamental fences and landscaping at Thorn.
Sunday, April 19 – Saturday, April 25 (On-Going)
Continuous Closures
Full U-turn underpass at Bridge C between Anthony and Vinton closed
Detour
Traffic on North Desert will need to proceed to Anthony, TX and utilize U-turn BridgeTraffic on South Desert will need to proceed to Vinton, TX and utilize U-turn Bridge
Crews will be conducting Bridge Demolition and Bridge Construction on U-turns under I-10.
South Desert between Valley Chile and Vinton Steel left lane closed
Detour: Traffic will be kept in one lane, with access to entrance ramp at Valley Chile, then continue in one lane of traffic until past bridge at Vinton Steel
Crews will be conducting work on walls.
North Desert between Transmountain and Isela Rubalcalva reduced to one lane
Crews will be working on roadway reconfiguration for South Desert.
North and South Desert at the Los Mochis intersection reduced to one lane
Crews will be working on Los Mochis intersection.
Artcraft Project
Monday, April 20 – Friday, April 24
9 a.m. – 4 p.m. (as needed)
SH-178 (Artcraft) east and westbound between New Mexico State Line and Doniphan alternate lane closures
Crews will be working on illumination and wall installations.
North Desert between Helen of Troy and Cheddars Restaurant alternate lane closuresSouth Desert between Charlie Clark Nissan and Blue Sky alternate lane closures
Crews will be loading and unloading material and equipment.
I-10 west and eastbound between Redd and Transmountain left lane closed
Crews will be working on median columns steel and erecting formwork.
Continuous Closure Until further notice 24/7
Monday, March 9 – End of Aug. 2026 (Approx. 5 months)
I-10 westbound exit ramp to Transmountain closed
Crews will be working on various constructions.
Borderland Expressway Phase 2 Project
Beginning at 4 a.m., Saturday, April 18 – 12 p.m. Sunday, April 19 (32 Hour Closure)
Martin Luther King (FM-3255) north and southbound between Loma Real and O-Hara (NM-404) full roadway closure
Local traffic will access businesses and residences between O’Hara (NM-404) and TX/NM State Line.
Detour: Traffic will use NM-404 (O’Hara Rd.), IH-10, LP-375 (Woodrow Bean/Transmountain) and US-54.
Stan Roberts (FM-2529) between McCombs and Martin Luther King (FM-3255) full roadway closure
Access to El Paso Electric Newman Power Plant will be available via McCombs and Stan Roberts intersection.
Crews will be working on a traffic switch to allow for construction of Martin Luther King (FM-3255) new road configuration.
Monday, April 20 – Friday, April 24
Daily, 7 a.m. – 5 p.m.
US-54 east and westbound between Mesquite Hills and McCombs alternate lane closuresMesquite Hills reduced to one lane between US-54 and Red Man. Flaggers will be on-site directing traffic as needed for haul trucks crossing Mesquite Hills
Flaggers will be on site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts intersection.
Crews will be transporting earth embankment into the project.
Safety Lighting on Mesa (SH20) & Dyer St. (BU-54) Project
Monday, April 20 – Friday, April 24
9 a.m. to 4 p.m.
SH-20 (Mesa) eastbound at Remcon intersection right lane closedSH-20 (Mesa) westbound at Camille intersection right lane closedSH-20 (Mesa) westbound at Thunderbird intersection right lane closedBU-54 (Dyer) eastbound at Hercules intersection right lane closed
Crews will be working on lighting improvements.
Runaway Truck Ramp Project
Continuous thru summer
Loop 375 (Transmountain) east and westbound between Northwestern and I-10 left lane closed
Crews will be installing arrest system.
Bridge Replacement at Alps Dr., Hollings St., and Concepcion St. Project
Continuous Closure Until Further Notice 24/7
Concepcion between Alameda and Paisano east and westbound closedAlps between Marie Tobin and Raymond Telles closedHollings between Raymond Telles and Hondo Pass closed
Detour: Please follow and proceed with detours in the area.
Crews will be working on culvert and bridge rehabilitation.
Technology Project on Bridge of the Americas and Zaragoza Port of Entry
Monday, April 20 – Friday, April 24
9:00 a.m. – 4:00 p.m.
Loop 375 (Border Highway) eastbound between San Marcial and Exit 58 to extend to Ramp W left shoulder and lane closed
Crews will be trenching and installing conduits.
Loop 375 (Border Highway) westbound between Fonseca and Paisano exit to include Fonseca entrance ramp to Loop 375 westbound two right lanes closed
Crews will be working on structures.
Ramp W (I-110 east) between Cordova Bridge and Pera Street shoulder and left lane closed
Crews will be installing wire conductors.
Signal Work – Loop 478 at Yandell and Montana at Trowbridge
Monday, April 20 – Friday, April 24
9 a.m. – 4 p.m.
Yandell between N Grama and Stevens all directions right lane closedCopia between Wyoming and Tularosa all directions right lane closed
Crews will be forming and placing concrete curb, sidewalk and installing drilled shafts for traffic signals and PED poles.
Road Repair
Sunday, April 19
5 a.m. – 4 p.m.
I-10 eastbound at Cotton three left lanes closed
Monday, April 20 – Thursday, April 23
9 p.m. – 6 a.m. (Nightly)
I-10 eastbound between Copia and Airway alternate lane closures
Guardrail Repair
9 a.m. – 4 p.m.
Monday, April 20
I-10 westbound between Viscount and Airway right lane and exit ramp at Airway closed
Tuesday, April 21
I-10 westbound between McRae and Hawkins right lane and exit ramp at Hawkins and entrance ramp at Viscount closed
Wednesday, April 22
I-10 westbound exit ramp at Piedras closedGateway West between Grama and Raynor left lane closed
Thursday, April 23
US-54 northbound between Altura and Pershing right lane closed
Friday, April 24
US-54 southbound between Cassidy and Pershing right lane closed
Concrete Work
Monday, April 20
9 a.m. – 4 p.m.
I-10 westbound between Airway and Geronimo right lane closed
Crews will be working on concrete traffic barrier.
Maintenance
Monday, April 20 – Friday, April 24
9 a.m. – 4 p.m.
Ramp N connecting between Loop 375 East and US-54 North ramp closed
Crews will be working on bridge joints.
North Desert between Medano and Helen of Troy right lane closed
Crews will be working on shoulder.
Loop 375 Widening Project
Monday, April 20 – Friday, April 24
Daily, 9 a.m. – 4 p.m.
Americas Avenue alternating lane closure north- and southbound between I-10 and Zaragoza Road (POE)
Crews will be installing roadway signs.
Horizon/Darrington Reconstruction Project
Monday, April 20 – Friday, April 24
Daily, 9 a.m. – 4 p.m.
Horizon Boulevard east and westbound alternating lane closures between Ashford Street and Desert Mesa DriveDarrington Road north and southbound alternating lane closures between Horizon Boulevard and Nunda Drive
Crews will be performing electrical work and paving operations.
Continuous closure until Friday, May 1 at 4 p.m.
Darrington Road southbound full closure between Horizon Boulevard and Homestead Drive
Crews will be working on southbound Darrington Road.
Continuous closure until May 2026
Pete La Rue Circle will follow detour entrance and exit at Roslyn Drive
Crews will be working on storm culverts, final subgrade, pavement operations and milling.
Safety Lighting Project
Monday, April 20 – Friday, April 24
Daily, 9 a.m. – 4 p.m.
Titanic Avenue east- and westbound right shoulder closures between Howard Street and Pandora StreetCopia Street north-and southbound alternating lane closure between Wyoming Avenue and Hueco AvenueDyer Street north-and southbound alternating lane closure between Kemp Avenue and Van Buren Avenue
Crews will be doing shoulder work.
FM 258 Safety Improvements Project
Monday, April 20 – Friday, April 24
Daily, 8:30 a.m. – 4 p.m.
Socorro Road westbound right lane closure between Winn Road and Belen Road
Crews will be working on installation of sidewalks, driveways, and curbs.
Montana Widening Project
Continuous closure until December 2026
Montana Avenue eastbound frontage road reduced to one lane from Saul Kleinfield to Tierra Este RoadMontana Avenue and Joe Battle Boulevard intersection, northbound and southbound of Joe Battle through lanes closed.Montana Avenue westbound frontage road reduced to two lanes from Tierra Este Road to Joe Battle Boulevard
Crews will be working on building underpass.
Purple Heart 375 Widening Project
Continuous closure until further notice
Purple Heart Highway north and southbound shoulder closures from Montana Avenue to Spur 601
Crews will widen main lanes and construct north and southbound frontage roads.
PROJECTS WITH CONTINUOUS CLOSURES
Sergeant Major Bridge Reconstruction Project
Continuous closure until December 2026
Purple Heart Highway (Loop 375) north- and southbound Sargent Major Exit Ramps closed
Crews will be working on ramp widening and shared use path extension.
I-10 Hudspeth Safety Rest Area
Continuous closure until December 2026
I-10 east and westbound shoulder closure between Fort Hancock and McNary
Crews will be working on utility installation.
Median Concrete Barrier Project
Continuous closure until further notice
Montana Avenue (US 62/180) east and westbound complete left lane closure between RM 124 and RM 126 (Guadalupe Peak)
Traffic will be reduced to one lane in work areas.
Closure is necessary for installation of median concrete barrier.
RM 652 Full Widening Project
Continuous closure until further notice
RM 652 westbound lanes reduced to one lane two-way traffic from FM 3541 to Kimble Draw Bridge
Closure is necessary for the reconstruction of the roadway.
RM 652 Full Depth Rehabilitation Project
Continuous closure until further notice
RM 652 east and westbound alternating lane closure 8.36 miles east of FM 3541 to Reeves County Line
Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with a 13-foot lane width restriction.
Closure is necessary for the construction of new roadway consisting of full depth rehabilitation
Please follow the detour signs in place on all projects. All work is dependent upon weather conditions.