Check out the latest transportation project updates in Pflugerville and Hutto, including roadway reconstructions, lane extensions, and parking improvements.

Pflugerville

Upcoming projects

Kelly Lane Phase 3

Project: The city will construct a four-lane roadway with a center median and four roundabout intersections from Moorlynch Avenue to Weiss Lane.

Update: Per city information, the transportation team anticipates 100% final utility designs by May.

Timeline: total project completion expected in early 2030Cost: $31.5 millionFunding source: city bond fundsParkway Drive

Project: Parkway Drive will be reconstructed into an urban road section with pavement, curb, gutter drainage, sidewalks and streetlights.

Update: Per city information, the project reached the final design and bidding preparation phase in March.

Timeline: expected to bid in MayCost: $3.4 millionFunding source: roadway impact fees, city bonds, community development block grantPfluger Farm Lane North

Project: A section of Pfluger Farm Lane will be widened and extended into a three-lane road.

Update: According to city information, the transportation team’s plan review was 100% complete as of March 30.

Timeline: expected to bid in SeptemberCost: $6.5 millionFunding source: city bond funds, roadway impact feesOngoing projects

Helios Way

Project:

Helios Way is being extended to improve access to the SH 130 Frontage Road and support industrial development.

Update: According to city officials, construction is underway on the new Helios Way right-in and right-out driveway.

Timeline: total project completion expected in mid-MayCost: $5.8 millionFunding source: Pflugerville Community Development Corporation Type B Sales TaxHutto

Upcoming projects

CR 199

Project:

The project will reconstruct CR 199 from CR 132 to FM 1660 South.

Update: In January, city council approved orders for coordination services with Union Pacific Railroad and the Texas Department of Transportation, including utility coordination services. Per city documents, the current Capital Improvement 5-Year Plan has funding for construction in Fiscal Year 2028.

Timeline: TBDCost: $20.5 millionFunding source: TBDFM 1660 South at US 79

Project: The project will construct turn lanes and make signal improvements at the intersection of FM 1660 South and US 79.

Update: According to city officials, design is 100% complete, but officials are awaiting approval from the Union Pacific Railroad to allow moving forward with bidding.

Timeline: expected to bid in early 2027Cost: $4.8 millionFunding source: 2022 general obligation bondsOngoing projects

Old Town parking and traffic improvements

Project:

The city is converting select downtown streets into one-way traffic to improve flow and safety, while adding parking. Changes include new parallel parking on East Street.

Update: According to city officials, crews completed the conversion of Main Street into a one-way road going southbound from Live Oak Street to Hwy. 79 on April 2. Crews will next work on phase 3 of the project, which will convert West Street into a one-way road going northbound. Construction is expected to begin this month.

Timeline: total project completion expected in 2026Cost: $500,000 for designFunding source: Hutto Economic Development Corporation fundingCompleted projects

Innovation Boulevard/Limmer Loop

Project:

Construction crews installed a new signal at the intersection, converting it from a two-way stop into a new four-lane signal stop intersection.

Update: According to city officials, crews activated the traffic signal April 7.

Timeline: completed in AprilCost: $2.23 millionFunding source: Capital Projects Fund

“>