Check out the latest Austin metro transportation updates, including a shared-use path in North Austin, parking improvements in downtown Hutto, and a new roundabout in Round Rock.
Upcoming projects
Austin Avenue pedestrian bridges
Project: This project will include construction of two pedestrian and bicycle bridges crossing the San Gabriel River in Georgetown, east of the existing Austin Avenue vehicular bridges.
Update: According to city officials, the revised design is tentatively scheduled to be complete in July 2027.
Timeline: 2023-TBDCost: $21 millionFunding sources: city of Georgetown, developer feesKelly Lane Phase 3
Project: The city of Pflugerville will construct a four-lane roadway with a center median and four roundabout intersections from Moorlynch Avenue to Weiss Lane.
Update: Per city information, the transportation team anticipates 100% final utility designs by May.
Timeline: total project completion expected in early 2030Cost: $31.5 millionFunding source: city bond fundsRoundabout at Sam Bass Road, Hairy Man Road Intersection
Project: A roundabout will be added to the intersection of Sam Bass and Hairy Man Roads in Round Rock to improve traffic flow and safety.
Update: According to Round Rock city officials, design is 60% complete.
Timeline: TBDCost: TBDFunding source: TBDOngoing projects
Cesar Chavez Street and Red Bluff Road
Project: The project includes safer intersections and lane configurations, protected bicycle lanes, new left-turn lanes, transit access and improved bus stops, and new pedestrian crossings. The city of Austin will extend the Colorado River Trail between Longhorn Dam and Shady Lane.
Update: The city held community meetings in April and is surveying residents on their feedback through May 11.
Timeline: summer 2027-summer 2028 or 2029Cost: $6.5 millionFunding sources: federal funding, Austin’s 2018 and 2020 Mobility BondsOld Town parking and traffic improvements
Project: The city of Hutto is converting select downtown streets into one-way traffic to improve flow and safety, while adding parking. Changes include new parallel parking on East Street.
Update: According to city officials, crews completed the conversion of Main Street into a one-way road going southbound from Live Oak Street to Hwy. 79 on April 2. Crews will next work on Phase 3 of the project, which will convert West Street into a one-way road going northbound. Construction is expected to begin this month.
Timeline: total project completion expected in 2026Cost: $500,000 for designFunding source: Hutto Economic Development Corporation fundingCompleted projects
Airport Boulevard Shared-Use Path
Project: The city of Austin completed a new shared-use path along the west side of Airport Boulevard between East 51st Street and Middle Fiskville Road.
Update: According to city officials, the project reached completion in early April.
Timeline: summer 2024-spring 2026Cost: $6.9 millionFunding source: 2016 Mobility Bond
“>