Plano City Council approved $2.7 million for residential paving improvements in central Plano at a meeting June 22.

In a nutshell

The city will be replacing 4,900 linear feet of street paving, sidewalks and barrier-free ramps, along with 250 linear feet of water line in some neighborhoods near Independence Parkway, according to city documents.

S.Y.B. Construction Co., a construction company that focuses mainly on projects in the Dallas-Fort Worth area, was awarded more than $2.73 million to start work in the city. Community Investment Program Engineering Manager Clay Lipscomb said construction for this project will start in July and likely be completed in summer 2027.

The specifics

The project will take place on six streets:

Glen Canyon DriveGrand Canyon DriveGranada PlacePinehurst DriveRoyal CircleLakeview TrailWork at Royal Circle will include water line replacements, while work at Lakeview Trail will only involve sidewalk repairs, per city documents.

“>