EL PASO, Texas (KTSM) — The Texas Department of Transportation has released a list of road closures for the week of July 31, 2026, that may affect your commute, including a full 12-hour closure on Interstate 10 East at Anthony and the return of weeklong night closures for the Artcraft Project.

I-10 Widening West Phase 2

Saturday, Aug. 1 and Saturday, Aug. 8, from 3 a.m. to 3 p.m.

Monday, Aug. 3 and Wednesday, Aug. 5; and Monday, Aug. 10 and Tuesday, Aug. 11, from 9 p.m. to 6 a.m.

I-10 eastbound closed at Anthony.

Follow detour. Crews will be placing beams.

Artcraft Project

Sunday, Aug. 2 – Thursday, Aug. 6, nightly from 9 p.m. to 6 a.m.

I-10 east and westbound between Loop 375 (Transmountain) and Artcraft full closure.

Crews will be placing steel girders.

Upcoming Closures

Sunday, Aug. 9 – Thursday, Aug. 13, nightly from 9 p.m. to 6 a.m.

Directional I-10 east and westbound between Loop 375 (Transmountain) and Artcraft full closure.

Crews will be placing deck panels on turnaround bridges.

Loop 375 Rehabilitation Project

Sunday, Aug. 2 – Tuesday, Aug. 4, nightly from 8 p.m. to 6 a.m.

Loop 375 (Border Highway) westbound between Fonseca and Oregon full closure.

Loop 375 (Border Highway) westbound entrance ramp from US-54 full closure.

Loop 375 (Border Highway) westbound entrance ramp from Delta full closure.

Wednesday, Aug. 5 – Thursday, Aug. 6, nightly from 8 p.m. to 6 a.m.

Loop 375 (Border Highway) westbound between Fonseca and Oregon alternate lane closures.

Loop 375 (Border Highway) eastbound between Schuster and Fonseca full closure.

Loop 375 (Border Highway) eastbound entrance ramp from Paisano full closure.

Loop 375 (Border Highway) eastbound entrance ramp from US-54 full closure.

Saturday, Aug. 8, from 6 a.m. to 5 p.m.

Loop 375 (Border Highway) eastbound between Schuster and Fonseca full closure.

Loop 375 (Border Highway) eastbound entrance ramp from Paisano full closure.

Loop 375 (Border Highway) eastbound entrance ramp from US-54 full closure.

Loop 375 (Border Highway) west and eastbound between Fonseca and Oregon alternate lane closures.

Crews will be working on milling, paving, and installing guardrail.

Sergeant Major Bridge Reconstruction Project

Monday, Aug. 3 – Wednesday, Aug. 5, from 12 a.m. to 3 p.m.

Purple Heart Highway (Loop 375) north and southbound right lanes between Sergeant Major Exit and Entrance Ramps.

Crews will be placing CRCP.

Thursday, Aug. 6, nightly from 9 p.m. to 5 a.m.

Purple Heart Highway (Loop 375) northbound right lanes, and southbound right and left lanes between Sergeant Major Exit and Entrance Ramps.

Crews will be pouring concrete.

Borderland Expressway Phase 2 Project

Monday, Aug. 3 – Friday, Aug. 7, from 7 a.m. to 5 p.m.

US-54 east and westbound between Mesquite Hills and McCombs alternate lane closures.

Mesquite Hills reduced to one lane between US-54 and Red Man.

Flaggers will be on-site directing traffic as needed for haul trucks crossing Mesquite Hills.

Flaggers will be on-site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts intersection.

Crews will be transporting earth embankment into the project.

Upcoming Closures

Monday, Aug. 10 and Tuesday, Aug. 11, from 6 a.m. to 6 p.m.

Stan Roberts east and westbound between McCombs and Martin Luther King full closure.

Access to EPEC Newman Power Plant will be available via McCombs and Stan Roberts intersection.

Detour: Traffic will be detoured using McCombs, US-54, and Martin Luther King.

Crews will be installing bridge beams.

Thursday, Aug. 13, from 6 a.m. to 6 p.m.

Full roadway closure of McCombs NB/SB between US54 and Stan Roberts.

Local traffic will be allowed to access residential neighborhood and golf course.

Traffic will be detoured using US54, Martin Luther King and Stan Roberts. See detour sheet below.

Crews will be installing bridge beams.

Road Repair

Monday, Aug. 3, from 9 p.m. to 6 a.m.

Gateway West at Geronimo traffic intersection complete closure.

Follow detour in place.

Guardrail Repair

Monday, Aug. 3, from 9 a.m. to 4 p.m.

South Desert between Thorn and Mesa right lane closed.

Tuesday, Aug. 4, from 9 a.m. to 4 p.m.

SH-20 (Mesa) eastbound at Belvidere right lane closed.

Wednesday, Aug. 5, from 9 a.m. to 4 p.m.

Oregon to Loop 375 (Border Highway) westbound complete closure.

Thursday, Aug. 6, from 9 a.m. to 4 p.m.

US-54 North at Fred Wilson right lane closed.

Friday, Aug. 7, from 9 a.m. to 4 p.m.

Loop 375 (Border Highway) eastbound between Midway and Yarbrough right lane closed.

Concrete Repairs

Monday, Aug. 3, from 9 a.m. to 4 p.m.

Gateway East between Boone and Raynolds left lane closed.

Tuesday, Aug. 4, from 9 a.m. to 4 p.m.

FM-2529 (McCombs) northbound between Blackhawk and Palomino right lane closed.

Maintenance

Monday, Aug. 3 – Friday, Aug. 7, from 9 a.m. to 4 p.m.

Loop 375 (Transmountain) westbound between Tom Mays Park entrance and Paseo Del Norte right lane closed.

Crews will be working on shoulder.

Spur 601 east and westbound between Chaffee and US-54 alternate lane closures.

Spur 601 westbound at Chaffee entrance ramp closed.

Spur 601 eastbound at Chaffee exit ramp closed.

Crew will be doing crack sealing.

Sunland Park westbound between Mesa Hills and I-10 right lane closed.

Crews will be milling and paving.

Gateway North between Yandell and Montana right lane closed.

Crews will be working on concrete.

Loop 375 (Border Highway) westbound at Exit 64 complete freeway closure.

Executive entrance ramp closed to Loop 375 (Border Highway) westbound.

Crews and Signal Shop removing signs.

Sunday, Aug. 9, from 4 a.m. to 5 p.m.

Ramp K between US-54 South and I-10 West closed.

Entrance ramp between Trowbridge and US-54 South closed.

Crews will be working on bridge joints.

Closure Links:

West Area Project Closures

I-10 Widening West Closures