Quick Read
Amazon (AMZN) is building a Texas gas plant permitted to emit 33 million tons of CO2 yearly, a figure that is double the output of America’s current dirtiest power station.
Amazon’s company-wide carbon emissions rose 16% last year, undermining its 2040 net-zero Climate Pledge as Andy Jassy guides $200 billion into AI infrastructure.
New York halted all new data center construction in July 2026 while Texas Governor Greg Abbott ordered audits of grid-connected data center projects.
It sounds nuts, but SoFi1 is giving new Active Invest users up to $3,000 in stock for a limited time, and all it takes is a $50 deposit to get started.2 See for yourself (Sponsor)
In rural West Texas, land-clearing crews are preparing a site for what could become the single largest source of carbon dioxide emissions among American power plants. Its only customer is an adjacent artificial intelligence data center financed by Amazon (NASDAQ:AMZN). If run at its full legal ceiling, the gas plant would emit roughly double the CO2 of today’s dirtiest U.S. power station.
24/7 Wall St. The Numbers Behind the Permit
The plant, developed by Pacifico Energy with Amazon financing, has been permitted by the Texas Commission on Environmental Quality to emit up to 33 million tons of CO2 per year. That figure is a legal ceiling, not a confirmed operating total, and generators routinely run below their permitted caps. Satellite imagery from late July 2026 shows active land-clearing, and three separate construction permits for data center buildings were filed in Texas in early August 2026, with first power targeted for Q1 2027.
The design is enormous: 35 natural gas turbines and up to 7.65 gigawatts of generating capacity, feeding a single Amazon Web Services campus. The reporting originated with a New York Times investigation published August 8, 2026, subsequently summarized by TechCrunch’s Anthony Ha the same day.
SoFi Active Invest is offering a limited-time promotion. Open an account, fund it with $50 or more, and you could receive up to $3,000 in complimentary stock for Active Invest accounts. See for yourself by clicking here now. (Sponsor)
Doubling the Current Record
The current dirtiest U.S. power station is the James H. Miller Jr. coal-fired plant in Quinton, Alabama, at roughly 16 million tons of CO2 per year. Amazon’s Pecos County project, if run at its permitted ceiling, would emit about twice that. The plant would be disconnected from the Texas public grid operated by ERCOT, at least initially, which is the basis for Amazon’s argument that ratepayers won’t foot the bill.
Story Continues
An Amazon spokesperson told the Times that the data center will “be powered by new on-site generation that won’t raise electricity costs for Texas families”. That framing sidesteps the atmospheric math: CO2 does not respect grid boundaries.
The Pledge Amazon Made in 2019
Amazon disclosed this year that its company-wide carbon emissions rose 16% last year, moving in the wrong direction relative to its Climate Pledge to zero out emissions by 2040. Asked about the tension, the spokesperson offered two lines: “The world looks different now than when we co-founded the climate pledge” and “Our commitment hasn’t changed.”
CEO Andy Jassy has guided investors to expect roughly $200 billion in capital expenditures across 2026, much of it for AI infrastructure. AWS grew 37% year over year in the second quarter, its fastest pace in 18 quarters. Compute demand is the constraint, and gas turbines are what can be built fastest at gigawatt scale.
An Industry Pattern, and a Political One
Amazon has plenty of company. AI operators across the sector are backing private gas plants to bypass grid queues that stretch years. Political tolerance is fraying: New York State halted construction of all new data centers in July 2026 over cost and grid concerns, and Texas Governor Greg Abbott on August 8, 2026 directed the Public Utility Commission and ERCOT to audit data center projects connecting to the state grid.
The signal to watch is concrete: whether the Pecos plant’s turbines are fired on schedule in the first quarter of 2027, and whether Amazon issues an updated Climate Pledge disclosure that reconciles a 7.65 gigawatt gas facility with a 2040 zero-carbon target. One of those documents is going to have to give.
Want Up To $3,000 In Stock? SoFi Is Giving New Active Invest Users Complimentary Stock
Looking to grow your money but unsure where to begin? SoFi Active Invest is offering a limited-time promotion—open a new Active Invest account, fund it with $50 or more, and you could receive up to $3,000 in complimentary stock.
From $0 commission trading3 to fractional shares4 and automated investing, this app is designed to simplify investing for everyone, whether you’re just starting or already experienced. Its easy to sign up and secure your bonus.(Sponsor)
Contact editorial@247wallst.com for any questions or corrections.