Check out five upcoming and ongoing transportation projects around Dallas-Fort Worth.
This list is not comprehensive.
Upcoming projects
Project: Coleman Street in Prosper is being widened to four lanes. One project will widen the roadway from two to four lanes between Gorgeous Road and Prosper Trail, and a second project will construct the remaining two southbound lanes of Coleman Street between Prosper Trail and Prosper High School.
Update: Both projects are nearing completion of the design phase. The town has acquired necessary right of way for both sections, and utility relocation is underway.
Timeline: winter 2026-winter 2027Cost: $6.65 million (Gorgeous Road to Prosper Trail), $3.77 million (Prosper Trail to Prosper High School)Funding source: town of Prosper
2. Hillcrest Road construction
Project: Hillcrest Road in Frisco will be updated from SH 121 to Main Street.
Update: The project is in the planning phase, with its design phase set to end in 2027.
Timeline: late 2027-late 2028Cost: $12 millionFunding source: city of Frisco, external funding
Ongoing projects
3. Carroll Boulevard utility installation
Project: This Atmos Gas project will see new gas lines installed along Carroll Boulevard in Denton from West Prairie Street to Pearl Street.
Update: Lanes will be closed along Carroll Boulevard as crews install the gas lines.
Timeline: late July-early SeptemberCost: not availableFunding source: Atmos Gas
4. John McCain Road bridge construction
Project: The project includes widening a culvert on Big Bear Creek and roadway improvements along John McCain Road in Colleyville. During construction, the bridge has remained closed.
Update: The project’s contractor began construction on stabilizing the road’s subgrade on the western end of the project in mid-August. Work on the project has been delayed because of issues related to the delivery and installation of a guardrail along the bridge.
Timeline: January-SeptemberCost: $540,000Funding source: city of Colleyville, Texas Department of Transportation
Project: Plano’s fifth year of ultra-thin asphalt overlay projects will extend the lifespan of four major roadways around the city:
Independence Parkway (Spring Creek Parkway to Parker Road)Legacy Drive (Coit Road to Custer Road)Park Boulevard (Midway Road to Preston Road)Parker Road (Independence Parkway to US 75)
Update: This year’s asphalt road work is expected to wrap by the end of September.
Timeline: July-September 2026Cost: $5.4 millionFunding source: city of Plano