EL PASO, Texas (KFOX14/ CBS4) — View the interactive TxDOT map and cameras here.

I-10 widening west closures

Phase 1

Monday, September 14 – Friday, September 18 (As Needed)

Daily, 9 a.m. – 4 p.m.

I-10 east and westbound between Los Mochis and Mesa alternate lane closuresNorth and South Desert between Los Mochis and Mesa alternate lane closuresEntrance ramp, exit ramp, and U-turn, east and westbound between Los Mochis alternate lane closures

Crews will be working on construction items.

Phase 2

Nightly, 9 p.m. – 6 a.m.

Monday, September 14 and Tuesday, September 15

South Desert between Anthony and Vinton full closure

Wednesday, September 16 and Thursday, September 17

North Desert between Vinton and Anthony full closure

Crews will be setting barrier.

Continuous Closures Until Further Notice 24/7

U-turn underpass at Bridge C between Anthony and Vinton full closure

Detour

Traffic on North Desert will need to proceed to Anthony, TX and utilize U-turn Bridge

Traffic on South Desert will need to proceed to Vinton, TX and utilize U-turn Bridge

Crews will be conducting Bridge Demolition and Bridge Construction on U-turns under I-10

South Desert between Valley Chile and Vinton Steel left lane closedSouth Desert between Vinton and Longwood left lane closed

Detour

Traffic will be kept in one lane, with access to entrance ramp at Valley Chile, then continue in one lane of traffic until past Bridge D at Vinton Steel

Crews will be working on walls.

North and South Desert at the Los Mochis intersection left lane closed

Crews will be working on Los Mochis intersection.

I-10 westbound exit ramp at North Desert between David and Nashua left lane closed

Crews will be working on the exit ramp.

South Desert between Transmountain and Isela Rubalcava left lane closed

Crews will be working on lane reconfiguration for South Desert at Tractor Supply.

Campus Park intersection at South Desert closed

Crews will be conducting paving operations.

Monday, September 14 – Saturday, September 19 (As Needed)

Daily, 9 a.m. – 4 p.m.

Nightly, 9 p.m. – 6 a.m.

I-10 east and westbound between Anthony and Mesa alternate lane closuresNorth and South Desert between Anthony and Mesa alternate lane closures

Crews will be conducting dirt work and miscellaneous removals.

I-10 westbound Bypass lanes between Mesa and Redd full closure

Detour: Traffic will continue along North Desert, through Thorn intersection, and enter I-10 before Redd.

I-10 eastbound Bypass lanes between Redd and Mesa full closure

Detour: Traffic will continue along South Desert, through the Thorn intersection, and enter I-10 before Mesa.

Crews will be working on completing the landscaping.

Artcraft Project

Monday, September 14 – Friday, September 18

9 a.m. – 4 p.m. (As Needed)

SH-178 (Artcraft) east and westbound between New Mexico State Line and Doniphan alternate lane closures

Crews will be working on ITS/Illumination and MSE wall installation.

North Desert between Helen of Troy and Cheddars Restaurant alternate lane closuresSouth Desert between Charlie Clark Nissan and Blue Sky alternate lane closures

Crews will be forming bent caps.

I-10 west and eastbound between Redd and Transmountain alternate lane closures

Crews will be working on median columns steel and erecting formwork.

I-10 eastbound at Redd exit ramp full closure

Crews will be placing form work for caps.

Monday, March 9 (Continuous Closure Until Further Notice 24/7)

I-10 westbound exit ramp to Transmountain closedSecondary temporary exit ramp to Transmountain open

Crews will be working on various constructions

Monday, August 31 Continuous Closure (8 week closure)

Paseo Del Norte Plaza access via Artcraft closure

Crews will be installing a water main.

Monday, August 10 Continuous Closure (4 – 6 week closure)

Intersection of Berringer through Artcraft access closure

Detour: Artcraft westbound traffic must exit at Doniphan and turn right, then proceed on Doniphan and turn right on East Borderland, then continue and turn right on Berringer.

Crews will be working on a water main bore.

Monday, June 1 Continuous Closures (8 to 9 week closure)

Santiago at Artcraft intersection closed

Crews will be working on a water main, storm drain, and paving.

Upcoming Closure

Thursday, September 24

9 p.m. – 6 a.m.

I-10 east and westbound between Transmountain and Artcraft full closure

Crews will be placing SBNB turnaround bridge deck.

Borderland Expressway Phase 2 Project

Monday, September 14 – Friday, September 18

Daily, 6 a.m. – 6 p.m.

US-54 east and westbound between Mesquite Hills and McCombs alternate lane closuresMesquite Hills reduced to one lane between US-54 and Red ManFlaggers will be on-site directing traffic as needed for haul trucks crossing Mesquite Hills

Daily, 7 a.m. – 5 p.m.

Flaggers will be on-site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts intersection

Crews will be working on bridge work and transporting earth embankment into the project.

Bridge Rehabilitation from Spur 1966 (Schuster) to Coldwell St. Project

Full Closure Until October 30, 2026 – 24/7

Paisano east and westbound between Spur 1966 (Schuster) and Coldwell St. main lanes closed

Crews will be working on bridge repairs.

ITS on Bridge of the Americas and Zaragoza Port of Entry Project

Monday, September 14 – Friday, September 18

9 a.m. – 4 p.m.

Loop 375 (Border Highway) eastbound between Zaragoza and Padres right lane and shoulder closed

Crews will be working on DMS #3 structure install.

Loop 375 (Border Highway) westbound between Padres and Zaragoza entrance ramp closed

Crews will be working on DMS #3 infrastructure.

Loop 375 (Border Highway) westbound between Padres and Zaragoza right lane and shoulder closed

Crews will be working on DMS #3 structure.

Loop 375 (Border Highway) eastbound between Midway and Columbia Apartments right lane and shoulder closed

Crews will be working on Sign 10 structure install.

Loop 375 (Border Highway) eastbound between Fonseca and Midway right lane and shoulder closed

Crews will be working on DMS #2 structure install.

US-54 southbound between Cambridge and Altura shoulder and right lane closed

Crews will be working on DMS #15 structure install.

Loop 375 eastbound at South Americas right lane and shoulder closed

Crews will be working on infrastructure for Sign 20 and 17.

Loop 375 westbound at South Americas right lane and shoulder closed

Crews will be working on infrastructure for Sign 17 and 20.

Safety Improvements -Median and Sidewalks at SH-20, BU-54A, IH-10, and McCombs

Monday, September 14 – Friday, September 18

9 a.m. – 4 p.m.

Alameda (SH-20) east and westbound between Tanton and Passmore right lane closedI-10 Frontage Road east and westbound between Geronimo and Airway

Crews will be working on prepping, blading, forming, and placing rebar for concrete placement.

Gateway East between Geronimo and Airway right lane closedGateway West between Airway and Geronimo right lane closed

Crews will be working on removing sidewalk, curb, and driveways, and placing new sidewalk, curb, and driveways.

Improve Traffic Signals – Loop 478 at Yandell and Montana at Trowbridge

Monday, September 14 – Friday, September 18

7 a.m. – 4 p.m.

Montana all directions between Chelsea Street and McAffee Place right lane closedTrowbridge all directions between Paisano and Forest Way right lane closed

Crews will be performing demolition and layout of new corners for the ADA ramps and the adjustments for the new traffic signals and PED poles.

Loop 375 Rehabilitation Project

Sunday, September 13 – Thursday, September 17

8 p.m. – 6 a.m. (Nightly)

Loop 375 (Border Highway) west and eastbound between Fonseca and Oregon full closureLoop 375 (Border Highway) westbound exit ramp to Paisano (Exit 20) full closureLoop 375 (Border Highway) westbound exit ramp to US-54 East and I-10 West full closure

Crews will be working on milling, paving, and guardrail.

BU-54A Safety Improvements

Monday, September 14 – Tuesday, September 15

Daily, 9 a.m. – 4 p.m.

Diana northbound at Vulcan between Meade and Riley left lane closed

Crews will be working on concrete work and traffic signal installations.

Wednesday, September 16

9 a.m. – 4 p.m.

Dyer alternating northbound shoulder and southbound right lane closed between Ashley and Mezquite Flor

Crews will be working on concrete work and traffic signal installations.

Thursday, September 17

9 a.m. – 4 p.m.

Dyer north and southbound alternating right lane closed between Quail Ave. and Sun Valley

Crews will be working on concrete work and traffic signal installations.

Road Repair

9 p.m. – 6 a.m. (Night)

Monday, September 14

-I-10 east between Copia and Raynolds two right lanes closedCopia entrance Ramp to I-10 east closed

Wednesday, September 16

I-10 eastbound between Viscount and Hawkins alternate lane closure

Thursday, September 17

I-10 westbound between Viscount and Hawkins alternate lane closure

Crews will be working on road repair.

Miscellaneous Concrete

Monday, September 14 – Friday, September 18

9 a.m. – 4 p.m.

I-10 westbound between Schuster and Executive right lane closed

Crews will be pouring concrete rip rap.

Guardrail Repair

9 a.m. – 4 p.m.

Monday, September 14

Loop 375 westbound (Transmountain/Woodrow Bean) at Railroad right lane closed

Wednesday, September 16

Loop 375 (Border Highway) between Fonseca and US-54 right lane closed

Thursday, September 17

SH-20 Doniphan westbound between La Union and Chanate right lane closed

Friday, September 18

Loop 375 (Transmountain) eastbound at Northwestern left lane closed

Maintenance

Monday, September 14 – Sunday, September 20

9 a.m. – 4 p.m.

Ramp C at US-54 North to I-10 West closed

Crews will be trimming trees.

I-10 East between Mesa and Resler left lane closed

Crews will be cleaning.

Sunday, September 20

5 a.m. – 4 p.m.

US-54 South two right lanes closedExit 21A closedI-10 East between US-54 and Raynolds right lane closedUS-54 North between I-10 and Yandell right lane closedRaynolds exit closed

Crews working on bridge joints.

Horizon/Darrington Reconstruction Project

Monday, September 14 – Friday, September 18

Daily, 8 a.m. – 5 p.m.

Horizon Boulevard east- and westbound alternating lane closures between Horizon Crossing Street, Thea Smith Drive, and Rodman StreetDarrington Road north- and southbound alternating lane closures between Kingston Road and Nunda Drive

Crews will be conducting electrical, concrete, sign, and landscaping work.

Continuous closure until September 2026

Darrington Road northbound traffic switch from Pete La Rue Circle to Roslyn DriveNorthbound access to Pete La Rue Circle, U-Turn on Darrington at the intersection of Roslyn and Alderwood Manor DriveDarrington Road southbound Full closure from Homestead Drive to Roslyn DriveDarrington Road and Roslyn/Alderwood Manor Drive intersection full closure

Crews will be installing water, sewer, and storm drain lines.

Safety Lighting Project

Monday, September 14 – Friday, September 18

Daily, 9 a.m. – 4 p.m.

Gateway East and West alternating lane and ramp closures from Raynolds Street to Paisano DriveTitanic Avenue east and westbound right shoulder closures between Howard Street and Pandora StreetCopia Street north and southbound alternating lane closure between Wyoming Avenue and Hueco AvenueDyer Street north and southbound alternating lane closure between Van Buren Avenue and Kemp AvenueI-10 from north and southbound alternating lane closures Acala Road to Finley Road

Crews will be doing shoulder work.

Montana Widening Project

Tuesday, September 15; Wednesday, September 16

Daily, 9 a.m. – 5 p.m.

Montana Avenue westbound frontage road left lane closure from Saul Kleinfeld to Tierra Este Road

Crews will be working on building underpass.

Thursday, September 17; Friday, September 18

Nightly, 9 p.m. – 5 a.m.

Montana Avenue eastbound right lane closure from Leticia Street to Joe Battle BoulevardThe northbound to southbound U-turn along Joe Battle Boulevard will be closed.

Crews will be placing Continuously Reinforced Concrete Pavement (CRCP).

Continuous closure until December 2026

Montana Avenue eastbound frontage road reduced to one lane from Saul Kleinfield to Tierra Este RoadMontana Avenue and Joe Battle Boulevard intersection, northbound and southbound of Joe Battle through lanes closed.Montana Avenue westbound frontage road reduced to two lanes from Tierra Este Road to Joe Battle Boulevard

Crews will be working on building underpass.

Purple Heart 375 Widening Project

Monday, September 14 – Friday, September 18

Daily 5 a.m. – 5p.m.

Loop 375 north- and southbound alternating lane closures between Montana Avenue and Spur 601

Crews will be doing shoulder work.

Continuous closure until further notice

Purple Heart Highway north- and southbound shoulder closures from Montana Avenue to Spur 601

Crews will widen main lanes and construct north- and southbound frontage roads.

Sergeant Major Bridge Reconstruction Project

Wednesday, September 16; Friday, September 18

Daily, 9 a.m. – 5 p.m.

Purple Heart Highway (Loop 375) north- and southbound right lane closure between Sergeant Major Exit and Entrance Ramps.

Crews will be placing Continuously Reinforced Concrete Pavement (CRCP).

RM 652 Full Widening Project

Monday, September 14; Friday, September 18

Daily, 7 a.m. – 4 p.m. (central time)

RM 652 east-and westbound alternating shoulder closures from FM 3541 to Kimble drain

Crews will conduct a mobile closure to reconstruct the shoulders.

PROJECTS WITH CONTINUOUS CLOSURES

I-10 Hudspeth Safety Rest Area

Continuous closure until December 2026

I-10 east- and westbound shoulder closure between Fort Hancock and McNary

Crews will be working on construction of Rest Area.

Please follow the detour signs in place on all projects. All work is dependent upon weather conditions.