A massive data center campus is making headway in Central Texas. Plans have been filed for two new data centers totaling to $1.2 billion in a booming tech hub outside of Austin.
EdgeConnex is currently in the process of building more than a dozen buildings for data center projects on a nearly 180-acre property in Cedar Creek. In May, EdgeConnex submitted plans for two other 730,000-square-foot data centers at the site, which were poised to begin construction in June.
Both TDLRs for the EdgeConnex project share the same address, 6402 FM 535, Cedar Creek, TX 78602 and construction site timelines. However, the buildings are labeled under two different project names, “EDCAUS15” and “EDCAUS16.”
The scope of work for both projects include a new construction of a “591,400-square-foot, one-story data center with supporting office space and associated site improvements,” per each TDLR. These buildings are designed to be a type II-B construction classification and will be fully protected by an automatic sprinkler system.
Construction on the buildings is set to begin in early November and the buildings are slated to be completed by mid-May 2028. All TDLR filings’ estimated start and completion dates are subject to change at any time.
MySA reached out to EdgeConnex for comment, but did not hear back prior to publication.