Screenshot of the City’s map for the Jefferson Complete Street project.

Dallas City Council recently approved an engineering design contract for the Jefferson Complete Street project.

The project is part of Proposition A in the 2024 Bond program, which provides $521.2 million for streets and transportation. The design will include a full street reconstruction with lighting, landscaping, and bicycle improvements for Jefferson Boulevard between North Hampton Road and North Polk Street. 

Halff Associates, Inc. was selected to provide services. The contract is limited to $2.66 million.

The design is expected to be completed in September 2029, with construction set to begin December 2029.

Share This Story, Choose Your Platform!

Victoria Hernandez is the Oak Cliff editor for Advocate Media. Prior to joining the Advocate, she wrote for Walton Insights, KUAF 91.3 and UARK Student Media. Victoria studied at the University of Arkansas, earning a B.A. in English/Journalism with minors in history and gender studies and a M.A. in Journalism with a Graduate Certificate in African and African American Studies. She can be reached by email at vhernandez@advocatemag.com