Also, 40% of the pipeline is in the ground as the legal fight over the project seems headed to court in the spring of next year

CORPUS CHRISTI, Texas — Corpus Christi’s Evangeline water project has reached two major milestones, with 40% of its 30-mile pipeline now in the ground and new connections to the Mary Rhodes pipeline.

But a legal challenge over water permits could complicate the project as the city works to secure additional water supplies for the Coastal Bend.

City Manager Peter Zanoni said the Evangeline project was connected to the Mary Rhodes pipeline during a recent shutdown for repairs. The connection work was moved up to take advantage of the pipeline being offline.

“About two weeks ago when the Mary Rhodes pipeline was off-line for repair that’s when we moved up the schedule of connecting the Evangeline project to the Mary Rhodes pipeline. So two taps if you will we put into the Mary Rhodes pipeline,” Zanoni said.

The connections are an important step toward integrating the Evangeline system with the pipeline that supplies most of Corpus Christi’s water.

The city is also considering purchasing water from two wells that have already been drilled and received production permits. Zanoni said the city wants to use the wells to test how well the system operates.

“There are two wells that have already been drilled and the production permits have already been approved. So we’re going to contemplate buying water from at least those two wells to make sure the system is working well,” Zanoni said.

However, the city of Sinton is challenging the permits over concerns that pumping groundwater could affect other wells in the area.

Corpus Christi City Councilwoman Carolyn Vaughn said she hopes the dispute can be resolved without stopping the project.

“I hope that they come back to the table because they are challenging the permits, that’s not a reason to just stop that happens all the time. This is a great project. It’s 24 MGD and if we can get it continue on, let’s see what happens,” Vaughn said.

The Evangeline project is designed to provide up to 24 million gallons of water per day.

Corpus Christi has already spent more than $100 million on the project, with another $280 million set aside. The overall project is expected to cost approximately $625 million.

City Councilman Mark Scott said stopping construction now could make the project significantly more expensive if the city has to restart work later.

“The reality is if you stop now and you start back up again later, the project gets to be you know significantly more expensive,” Scott said.

Scott expects the city will eventually obtain the necessary permit, but the legal challenge could take years to resolve.

For Corpus Christi, the project represents another effort to diversify the city’s water supply as officials work to secure more water for the future.