HARRIS COUNTY, Texas (KTRK) — Harris County officials say they don’t know whether a one-year extension is enough time to complete a series of flood control projects, and millions of dollars in grant funding could be at risk if the work isn’t finished on time.

The county received more than $300 million in grant money three years ago for 11 projects that were supposed to be finished by February. The county received a one-year extension last month, but questions remain about whether that will be enough.

The Harris County Flood Control District told ABC13 it would present details on the projects to Commissioner’s Court last week, but that presentation never happened.

Precinct 2 Commissioner Adrian Garcia said he delayed it because the presentation lacked details.

“I still have not gotten that full information from the executive director,” Garcia said. “So, I didn’t think we were ready for that conversation yet.”

Prior to the extension, the county made changes this summer to speed up the process. They proposed swapping projects and changing the scope.

The Texas General Land Office, which oversees the grant money, sent a letter to the county the day before the Commissioner’s Court meeting laying out its concerns.

In the letter, Commissioner Dawn Buckingham said, “Given Harris County’s repeated inability to fully execute promised projects even within the newly available timeframe, the GLO cannot move forward with the project swaps. This decision is not based on administrative burden. Rather, Texas still has substantial unmet needs from Hurricane Harvey, and the state cannot risk funds lapsing back to HUD because of Harris County’s eventual failure to complete these projects.”

On Monday, GLO spokesperson Brittany Eck sent ABC13 a statement going even further.

“In the past six months, HCFCD has only provided vague ideas and undefined concepts,” Eck said. “Unfortunately, that is not how the HUD grant process works. Subrecipients cannot piecemeal projects and Frankenstein together proposals.”

Last week, Harris County Judge Lina Hidalgo told ABC13 that projects are moving faster.

“Does that get us the projects done as quickly as I would like them done? No,” Hidalgo said. “It just means that hopefully we will not have to give any money back, which is looking like we won’t, like we were before.”

On Monday, ABC13 again asked the flood control district for an update on the projects, and if they would share last week’s presentation. A spokesperson told ABC13 they will provide an update at next month’s meeting.

Garcia said finishing the work is critical for his community.

“These projects are so important,” Garcia said. “As you heard me mentioning earlier, Precinct 2 is on the downstream side of five counties, so getting these projects done is critical for my community.”

If the projects aren’t completed in time, the state says the county could be responsible for millions of dollars to finish them.