Check out three transportation updates in Richardson.

Ongoing projects

Custer Parkway reconstruction

Project: Street reconstruction of Custer Parkway from Campbell Road to Renner Road and street panel replacement from Renner Road to State Highway 190.

Update: Concrete replacements on the northbound lanes from Lookout Drive to Campbell are ongoing and expected to be completed this spring. Traffic signal replacements at the intersections at Renner and Campbell are also ongoing and expected to be completed by spring.

Timeline: fall 2024-fall 2026Cost: $23.1 millionFunding source: city of RichardsonArterial street maintenance

Project: This project will rehabilitate various street segments throughout the city.

Update: Construction on Floyd Road from Belt Line Road to US 75 is underway. Construction on Renner Road from US 75 to Brand Road is expected to begin in winter 2026.

Timeline: summer 2025-summer 2026Cost: $2 millionFunding source: city of RichardsonBelt Line Road improvements

Project: Drainage, utility and pavement improvements at Belt Line Road and pavement improvements along Cottonwood Drive.

Update: Culvert installation at Belt Line and along Cottonwood is complete. Paving on Cottonwood is currently ongoing.

Timeline: fall 2024-winter 2026Cost: $4.7 millionFunding source: city of Richardson

“>