Check out five road projects happening around Dallas-Fort Worth.

Collin County construction

1. Custer Road

Project: The North Texas Municipal Water District is currently working to replace an aging pipeline along Custer Road in Plano.

Update: According to a Plano city news release, 4,900 feet of the 9,100-foot pipeline have been installed. Permanent paving at West 15th Street and Pitman Drive will be scheduled pending water testing.

Timeline: February 2025-October 2026Cost: $18 millionFunding source: North Texas Municipal Water District2. Legacy Drive intersection improvements

Project:

Crews are working to improve intersections in west Plano, including Corporate Drive and Legacy Drive.

Update: Several lanes along Legacy Drive will see closures for ongoing construction.

Timeline: September 2025-June 2026Cost: $2.59 millionFunding source: city of Plano3. US 75 expansion

Project:

The project will expand US 75 into five lanes by converting existing high-occupancy vehicle lanes into “technology lanes,” which will have designated time periods for HOV travel but will be open for all drivers at other times.

Update: Richardson crews are on track to complete the project by summer 2026.

Timeline: March 2024-summer 2026Cost: $57 millionFunding source: Texas Department of TransportationDenton County

4. Bonnie Brae Street Phase 6 widening

Project:

Workers will widen the road with two additional lanes and a pedestrian and bike path alongside the road in Denton. The phase is part of a multiyear seven-phase expansion project.

Update: Contractors began work to modify the soil in preparation for the roadway expansion at the northern part of Bonnie Brae Street.

Timeline: January 2025-April 2027Cost: $38 millionFunding sources: city of Denton, Denton County5. Alice Street reconstruction

Project:

The project will replace the waterline, curb, gutter and portions of the sidewalk along Alice Street in Denton. The project’s scope also includes a total roadway reconstruction. This project is funded from the $50 million Neighborhood 2 bond approved by voters in 2019.

Update: Crews are nearly complete with concrete work with final paving scheduled for late April.

Timeline: September 2025-JuneCost: $1.46 millionFunding source: city of Denton