Check out the latest Austin metro transportation updates, including a shared-use path in North Austin, parking improvements in downtown Hutto, and a new roundabout in Round Rock.

Upcoming projects

Austin Avenue pedestrian bridges

Project: This project will include construction of two pedestrian and bicycle bridges crossing the San Gabriel River in Georgetown, east of the existing Austin Avenue vehicular bridges.

Update: According to city officials, the revised design is tentatively scheduled to be complete in July 2027.

Timeline: 2023-TBDCost: $21 millionFunding sources: city of Georgetown, developer feesKelly Lane Phase 3

Project: The city of Pflugerville will construct a four-lane roadway with a center median and four roundabout intersections from Moorlynch Avenue to Weiss Lane.

Update: Per city information, the transportation team anticipates 100% final utility designs by May.

Timeline: total project completion expected in early 2030Cost: $31.5 millionFunding source: city bond fundsRoundabout at Sam Bass Road, Hairy Man Road Intersection

Project: A roundabout will be added to the intersection of Sam Bass and Hairy Man Roads in Round Rock to improve traffic flow and safety.

Update: According to Round Rock city officials, design is 60% complete.

Timeline: TBDCost: TBDFunding source: TBDOngoing projects

Cesar Chavez Street and Red Bluff Road

Project: The project includes safer intersections and lane configurations, protected bicycle lanes, new left-turn lanes, transit access and improved bus stops, and new pedestrian crossings. The city of Austin will extend the Colorado River Trail between Longhorn Dam and Shady Lane.

Update: The city held community meetings in April and is surveying residents on their feedback through May 11.

Timeline: summer 2027-summer 2028 or 2029Cost: $6.5 millionFunding sources: federal funding, Austin’s 2018 and 2020 Mobility BondsOld Town parking and traffic improvements

Project: The city of Hutto is converting select downtown streets into one-way traffic to improve flow and safety, while adding parking. Changes include new parallel parking on East Street.

Update: According to city officials, crews completed the conversion of Main Street into a one-way road going southbound from Live Oak Street to Hwy. 79 on April 2. Crews will next work on Phase 3 of the project, which will convert West Street into a one-way road going northbound. Construction is expected to begin this month.

Timeline: total project completion expected in 2026Cost: $500,000 for designFunding source: Hutto Economic Development Corporation fundingCompleted projects

Airport Boulevard Shared-Use Path

Project: The city of Austin completed a new shared-use path along the west side of Airport Boulevard between East 51st Street and Middle Fiskville Road.

Update: According to city officials, the project reached completion in early April.

Timeline: summer 2024-spring 2026Cost: $6.9 millionFunding source: 2016 Mobility Bond

“>