Check out three road project updates in League City.
Completed project
League City Parkway right-turn lane
Project: An eastbound right-turn lane was designed west of Butler Road to west of the I-45 southbound frontage road, and tied to the Texas Department of Transportation’s right-turn lane, according to city officials.
Update: The project is complete and the roadway is now open to traffic.
Timeline: completed in MarchCost: $2.08 millionFunding source: Galveston County bond fundsOngoing project
FM 518 at Country Lane intersection improvements
Project: This is a full intersection rebuild at FM 518 and Country Lane, including signal upgrades, mast arm installation and safety enhancements, according to city officials.
Update: Construction started in late April due to a wait on signal equipment.
Timeline: slated to wrap in the fallCost: $504,000Funding sources: city reinvestment fundsUpcoming project
Traffic signal at Lawrence Road and Village Way
Project: The project scope includes a design and rebuild of the traffic signal at the intersection, according to city officials.
Update: Construction is slated to begin in May.
Timeline: estimated to take a year to complete, varies depending on delivery of new signal apparatusCost: $573,000Funding sources: city reinvestment funds
“>