Upcoming projects

1. US 75 Green Ribbon project

Project: The work will add enhancements to landscaping, erosion control, irrigation and new decorative rock to key intersections along the US 75 corridor, including Stacy Road, McDermott Drive and Bethany Drive.

Update: City officials are coordinating with the Texas Department of Transportation to advertise the construction project.

Timeline: summer 2026-end of 2026Cost: $1.38 millionFunding source: TxDOT, city of AllenOngoing projects

2. Street and alley repairs

Project: The annual project includes the replacement of deteriorated street and alley pavement and upgrades to accessible ramps in various locations throughout Allen in an effort to enhance accessibility and extend the lifespan of the roadway network.

Update: Construction work for the alleys in the Oak Hill neighborhood have been completed.

Timeline: completion slated for March 2027Cost: $4.98 millionFunding source: city of Allen3. Highway Safety Improvement Program

Project: Updates include modernized traffic signals, upgraded equipment, increased capacity and enhanced pedestrian features.

Update: Construction is wrapping up with three intersections remaining at Century Parkway and Bethany Drive, Greenville Avenue and Bethany Drive, and Main Street and Greenville Avenue.

Timeline: construction to wrap up by summer 2026Cost: $5.8 millionFunding source: city of Allen, TxDOT

“>