Learn more about ongoing and future road projects in Hutto and Pflugerville.
Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane.
Update: Full utility design was completed in May.
Timeline: completion expected in March 2028Cost: $36 millionFunding source: city bond fundsParkway Drive
Project: The road will be reconstructed with pavement, curb, drainage, sidewalk and streetlight improvements.
Update: The project went to bid in May.
Cost: $3.2 millionFunding source: city bond funds, roadway impact feesPfluger Farm Lane North
Project: The road will be widened to three lanes and extended to connect to SH 45.
Update: The city anticipated receiving 60% of design plans by the end of June.
Cost: $6.7 millionFunding source: city bond funds, roadway impact fees
“>
Project: The road will connect to SH 130 Frontage Road.
Update: The completion date was extended to August.
Timeline: completion was expected in MayCost: $5.8 millionFunding source: Type B sales taxCR 199
Project: The project will reconstruct CR 199 from CR 132 to FM 1660 South.
Update: Funding will be allocated in 2028
Timeline: TBDCost: $20.5 millionFunding source: TBDFM 1660 South at Hwy. 79
Project: New turn lanes and signals will be added to the intersection of FM 1660 South and Hwy. 79.
Update: Design is complete.
Timeline: expected to bid in early 2027Cost: $4.8 millionFunding source: 2022 general obligation bondsOld Town parking and traffic improvements
Project: The city is converting downtown streets into one-way traffic.
Update: Main Street was converted to a one-way in April.
Timeline: total project completion expected in 2026Cost: $500,000 for designFunding source: Hutto Economic Development Corp. funding