Project: Crews will replace a waterline and pavement on G Avenue between 14th and 15th streets. Improvements will also add on-street parking, enhance sidewalks and update traffic signals.

Update: Community Investment Project Engineering Manager Clay Lipscomb said the project is in its final design phase and construction will start in Quarter 4 of 2026.

Timeline: July-December 2026Cost: $374,800Funding source: city of Plano2. Spring Creek Corridor Intersection Improvements

Project: New turning lanes, concrete pavement, barrier free ramp reconstruction, sidewalk replacement and signal modifications along Spring Creek Parkway at Jupiter Road, Chase Oaks Drive, Ohio Drive, Preston Meadow Road and Parkwood Boulevard.

Update: Lipscomb said easements for the project are almost completed and designs are done. Construction is estimated to start in 2027.

Timeline: January 2027-January 2029Cost: $8 millionFunding source: city of Plano3. Shady Brook Trail Renovations at Midway