The city of Pflugerville has several transportation projects in various stages of progress. Learn more about road projects in your community.

Upcoming projects

Kelly Lane Phase 3

Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane.

Update: Full utility design was completed in May. If utility relocations continue as scheduled, the project will go out to bid in April 2027.

Timeline: completion expected in March 2028Cost: $36 millionFunding source: city bond fundsParkway Drive

Project: The road will be reconstructed with pavement, curb, drainage, sidewalk and streetlight improvements.

Update: The project was anticipated to bid in May.

Cost: $3.2 millionFunding source: city bond funds, roadway impact feesPfluger Farm Lane North

Project: The road will be widened to three lanes and extended to connect to SH 45.

Update: The city received a 60% design plan draft in June.

Cost: $6.7 millionFunding source: city bond funds, roadway impact fees

Ongoing projects

I-35 Capex North Expansion

Project: This project will add one tolled lane to I-35 from US 290 East to SH 45, with a diverging diamond intersection at Wells Branch Parkway.

Update: Work is underway to widen frontage roads from Grand Avenue Parkway to SH 45.

Timeline: March 2023-early 2029Cost: $606 millionFunding source: funded by Capital Area Metropolitan Planning Organization and the Texas Department of Transportation