Crews are working to remove the demolished deck of the southbound Austin Avenue vehicular bridge, as of a June 22 update from the city.

Catch up on this transportation project, and others in Georgetown, below.

Upcoming projects

Williams Drive medians

Project: The project will construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared-use path on the north side of the road.

Update: The Texas Department of Transportation is reviewing contractor bids, and officials anticipate construction starting this summer.

Timeline: summer 2026-2027Cost: $19.7 millionFunding sources: city of Georgetown, traffic impact fees, federal grants, tax increment financing

SE Inner Loop

Project: A 2.91-mile stretch of SE Inner Loop will be widened to a four-lane, divided road from Hwy. 29 to FM 1460. A shared-use path will also be added.

Update: Utility relocations are underway from FM 1460 to Southwestern Boulevard. The advertising and bidding process will follow.

Timeline: 2026-28Cost: $70.6 millionFunding sources: city of Georgetown, Georgetown Transportation Enhancement Corp.

Ongoing projects

Shell Road widening

Project: The city will widen Shell Road from Williams Drive to Sycamore Street to four lanes with a raised median, shared-use path, and left- and right-turn lanes.

Update: As of June, the majority of utility work has been completed. Crews are working on paving.

Timeline: January 2026-December 2027Cost: $19 millionFunding source: city of Georgetown

Rockride Lane

Project: Rockride Lane is being upgraded to a two-lane collector with a continuous center left-turn lane and a 10-foot-wide shared-use path from SE Inner Loop to Sam Houston Avenue.

Update: The contractor has begun work to install the permanent signal at the Sam Houston and Rockride Intersection.

Timeline: 2025-26Cost: $12 millionFunding source: city of Georgetown

Austin Avenue vehicular bridges

Project: This project includes reconstruction of two vehicular bridges crossing the San Gabriel River.

Update: The southbound Austin Avenue bridge decks were demolished starting in early June, and reconstruction will take approximately two months. The contractor will then do the northbound bridge decks.

Timeline: 2024-27Cost: $12.8 millionFunding sources: city of Georgetown, developer fees

Completed projects

DB Wood Road Phase 1

Project: The project adds four lanes, a center turn lane and a shared-use path from Hwy. 29 to Oak Ridge Road.

Update: The project is substantially complete, and all four lanes of traffic are open. A ribbon-cutting ceremony was held in July.

Timeline: 2023-26Cost: $29.6 millionFunding source: city of Georgetown