Workers continue construction on Building D adjacent to Rusty Franklin Field at Plano East Senior High School. Photo Bob Wieland/Murphy Monitor

Renovation work at Plano East Senior High School begun in February of 2025 is scheduled for completion in the first half of next year, according to a report by school district officials.

Tony Pearson, director of planning and new construction, updated the Plano ISD Board of Trustees on the progress of construction under the 2022 bond program. 

Pearson said at the Tuesday, Aug. 18, board work session that contracts called for $58.4 million in construction including renovation of about 7,000 square feet in Building D, major locker room renovations and two new gym floors. 

Read the full story in the August 27th edition. Stay informed — subscribe to Murphy Monitor.