Corpus Christi’s $625 million Evangeline water pipeline is 40% complete and now connects to the Mary Rhodes system, while a groundwater permit challenge from Sinton heads toward court.

(UI) — Construction of Corpus Christi’s $625 million Evangeline water project has reached two milestones, with 40% of the planned 30-mile pipeline installed and new connections completed to the existing Mary Rhodes Pipeline. The project is designed to expand water supplies for Corpus Christi and the surrounding Coastal Bend region. 

City Manager Peter Zanoni said crews installed two connections to the Mary Rhodes Pipeline during a scheduled shutdown for repairs, allowing the work to be completed ahead of its original schedule. According to KIII News, the connection will integrate the Evangeline system with a pipeline that supplies most of the city’s water.

Corpus Christi is also considering purchasing water from two existing wells with approved production permits to test system performance. However, the City of Sinton is challenging groundwater permits over concerns that pumping could affect nearby wells, creating potential legal complications for the project.

The Evangeline system is designed to deliver up to 24 million gallons of water per day, KIII reported. Corpus Christi has spent more than $100 million on the project, with another $280 million set aside and total costs estimated at approximately $625 million. City officials have warned that suspending construction could increase costs if work must restart later, as the dispute over permits moves toward potential court proceedings next spring.