{"id":413509,"date":"2026-08-22T03:46:13","date_gmt":"2026-08-22T03:46:13","guid":{"rendered":"https:\/\/www.newsbeep.com\/us-tx\/413509\/"},"modified":"2026-08-22T03:46:13","modified_gmt":"2026-08-22T03:46:13","slug":"ercots-data-center-audit-will-last-until-late-2026-officials-say-central-austin","status":"publish","type":"post","link":"https:\/\/www.newsbeep.com\/us-tx\/413509\/","title":{"rendered":"ERCOT\u2019s data center audit will last until late 2026, officials say | Central Austin"},"content":{"rendered":"<p>Texas\u2019 audit of hundreds of proposed data centers will likely wrap up by the end of the year, grid officials said Aug. 20.<\/p>\n<p>Up to 300 proposals will be audited to ensure they meet certain criteria before the data centers can begin connecting to the state electric grid. If all the plans are approved, these facilities alone could use about 200 gigawatts of electricity\u2014more than twice Texas\u2019 91-gigawatt <a href=\"https:\/\/www.ercot.com\/static-assets\/data\/news\/content\/a-peak-demand\/all-time-records.htm\" rel=\"nofollow noopener\" target=\"_blank\">peak demand record<\/a>, which was set on July 22.<\/p>\n<p>How we got here<\/p>\n<p>Texas is home to the nation\u2019s fastest-growing data center market, with <a href=\"https:\/\/www.bloomenergy.com\/wp-content\/uploads\/2026-power-report.pdf#page=5\" rel=\"nofollow noopener\" target=\"_blank\">a January report from Bloom Energy<\/a> projecting that the state will see a 142% increase in its share of the data center industry by the end of 2028.<\/p>\n<p>In 2022, about 2.6 gigawatts of large electricity users, such as industrial facilities and data centers, joined the Texas grid, <a href=\"https:\/\/www.ercot.com\/files\/docs\/2026\/07\/29\/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf\" rel=\"nofollow noopener\" target=\"_blank\">according to the Electric Reliability Council of Texas<\/a>. About 6.4 gigawatts of large projects connected to the grid in 2024, jumping to 61 gigawatts of planned and approved projects this year. ERCOT is tracking approximately 474 gigawatts of large projects that are seeking to connect to the grid in the coming years\u201490% of which are data centers.<\/p>\n<p>As residents from around the state raise concerns about the impact of data centers\u2014including light and noise pollution, facilities\u2019 water use and changes in electricity costs\u2014state officials are grappling with how to manage the booming industry.<\/p>\n<p><a href=\"https:\/\/communityimpact.com\/central-austin\/texas-legislature\/texas-to-pause-new-data-center-projects-until-audit-is-conducted-gov-abbott-says\/\" rel=\"nofollow noopener\" target=\"_blank\">On Aug. 3<\/a>, Gov. Greg Abbott directed ERCOT and the Public Utility Commission of Texas to audit proposed data centers to ensure developers provide information about the tax exemptions they are receiving; their plans for water and electricity use; how they will limit disturbances to local communities; and who owns each proposed facility. No new data centers will be approved until the audit is complete and any facilities that fail the audit \u201cmust be denied,\u201d Abbott said.<\/p>\n<p>More details<\/p>\n<p>During recent PUC meetings, officials clarified they would audit about 250-300 facilities that were previously identified for ERCOT\u2019s \u201cBatch Zero\u201d study. That <a href=\"https:\/\/www.ercot.com\/files\/docs\/2026\/06\/18\/ERCOT-Trending-Topic-New-Batch-Connection-Process-for-Large-Electricity-Users.pdf\" rel=\"nofollow noopener\" target=\"_blank\">study<\/a> was designed to give ERCOT a big-picture view of the large facilities in line to join the grid and ensure enough power will be available to serve them, although the study was postponed while facilities are audited.<\/p>\n<p>Prior to Abbott\u2019s order, ERCOT had planned to complete its first batch study in April, at which point it would begin approving data centers from that batch. Officials said they did not know how the audit process would impact the full batch schedule.<\/p>\n<p>\u201cWe will not have the study done by [April]\u2014we\u2019re still working on what that new timeline might be once we get done with the [audit and] verification process, and there&#8217;s plenty of time to address that,\u201d Chad Seely, ERCOT\u2019s general counsel and chief compliance officer, said Aug. 20. \u201cSo it&#8217;s not an essential issue right now to decide what the timeline is for the batch zero study process.\u201d<\/p>\n<p>How it works<\/p>\n<p>Only large loads, or facilities that are expected to use at least 75 megawatts of electricity, will be included in the audit. However, officials said ERCOT will also survey proposed data centers that would use 25 megawatts of electricity or more and collect information about those facilities&#8217; impact on local communities.<\/p>\n<p>\u201cYou&#8217;ll get descriptive statistics out of that: How much the <a href=\"https:\/\/communityimpact.com\/central-austin\/texas-legislature\/texas-spends-billions-on-tax-breaks-for-data-centers-theres-a-bipartisan-legislative-push-to-repeal-them\/\" rel=\"nofollow noopener\" target=\"_blank\">tax abatements<\/a> are, how much water [they&#8217;re using], and then from that we can come back to you all &#8230; as we&#8217;re trying to bring on these data centers,&#8221; PUC chairman Thomas Gleeson said during <a href=\"https:\/\/communityimpact.com\/central-austin\/texas-legislature\/live-updates-local-officials-request-larger-role-in-data-center-oversight-regulation\/\" rel=\"nofollow noopener\" target=\"_blank\">an Aug. 19 legislative hearing<\/a>. &#8220;That&#8217;s really the goal, as we understand it from the governor&#8217;s directive, is to gather that information &#8230; so it can help inform decisions going forward.&#8221;<\/p>\n<p>Medium-sized data centers that are not being audited do not have to wait to connect to the grid, Seely said Aug. 20.<\/p>\n<p>\u201cERCOT does not have that authority to stop them,\u201d he told the PUC. \u201cThose medium-sized loads will work directly with their utility through their interconnection process, so it&#8217;s really up to the local utility on where they are in that process as far as connecting them to the grid.\u201d<\/p>\n<p>Information <a href=\"https:\/\/interchange.puc.texas.gov\/Documents\/59142_52_1675838.PDF\" rel=\"nofollow noopener\" target=\"_blank\">shared with the PUC<\/a> on Aug. 20 shows that officials plan to:<\/p>\n<p>Collect information on large and medium-sized data center proposals through NovemberRelease a \u201cbatch zero eligibility verification report\u201d and \u201ccommunity impact review report\u201d on Dec. 10Present information from those reports during a Dec. 17 PUC meeting<\/p>\n","protected":false},"excerpt":{"rendered":"Texas\u2019 audit of hundreds of proposed data centers will likely wrap up by the end of the year,&hellip;\n","protected":false},"author":2,"featured_media":413510,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[11],"tags":[144255,144259,132,134,133,136701,144253,144258,6083,3413,144257,144252,4872,42729,13847,139434,118462,144256,69690,293,118464,144254],"class_list":["post-413509","post","type-post","status-publish","format-standard","has-post-thumbnail","category-austin","tag-abbott-data-center-audit","tag-audit-deadline","tag-austin","tag-austin-headlines","tag-austin-news","tag-batch-study-process","tag-chad-seely-ercot","tag-data-center-audit-timeline","tag-electric-reliability-council-of-texas","tag-ercot","tag-ercot-batch-zero","tag-ercot-data-center-audit","tag-gov-greg-abbott","tag-pablo-vegas","tag-public-utility-commission-of-texas","tag-texas-data-center-audit","tag-texas-data-center-laws","tag-texas-data-center-rules","tag-texas-data-centers","tag-texas-legislature","tag-thomas-gleeson","tag-who-is-audited-texas-data-centers"],"_links":{"self":[{"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/posts\/413509","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/comments?post=413509"}],"version-history":[{"count":0,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/posts\/413509\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/media\/413510"}],"wp:attachment":[{"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/media?parent=413509"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/categories?post=413509"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.newsbeep.com\/us-tx\/wp-json\/wp\/v2\/tags?post=413509"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}